GAIL Revises Completion Schedule for Key Pipeline Sections to March 2026
GAIL (India) Limited has extended the completion schedule for two key pipeline sections from December 2025 to March 2026, as approved by the Board of Directors on January 03, 2026. The delay affects the Durgapur-Haldia section of the Jagdishpur-Haldia-Bokaro-Dhamra Pipeline and the Dhamra-Haldia Pipeline section, both facing challenges in obtaining Right of Use permissions and fisheries front availability. Despite these delays, both projects show significant progress with the main pipeline having 3,252 kilometers laid and 3,119 kilometers commissioned out of 3,306 kilometers authorized length.

*this image is generated using AI for illustrative purposes only.
GAIL (India) Limited has announced a three-month extension in the completion schedule for two key pipeline sections, moving the target date from December 2025 to March 2026. The revision was formally approved by the company's Board of Directors during their meeting held on January 03, 2026, which commenced at 02:00 p.m. and concluded at 04:30 p.m.
Pipeline Projects Overview
The revision affects two significant pipeline sections under GAIL's major infrastructure development program. Both projects represent critical components of India's natural gas distribution network and are part of the company's broader pipeline expansion strategy.
| Pipeline Project | Authorized Length | Pipeline Laid | Pipeline Commissioned | Balance Section |
|---|---|---|---|---|
| Jagdishpur-Haldia-Bokaro-Dhamra | 3,306 Kms | 3,252 Kms | 3,119 Kms | Kolkata-Haldia Section |
| Dhamra-Haldia | 240 Kms | 217 Kms | 150 Kms | Dhamra-Haldia (West Bengal) |
Completion Schedule Revision Details
The company has revised the completion timeline for both remaining sections due to operational challenges. The Durgapur-Haldia section of the Integrated Jagdishpur-Haldia-Bokaro-Dhamra Pipeline Project and the Dhamra-Haldia Pipeline section will now be completed by March 2026 instead of the originally planned December 2025.
| Parameter | Details |
|---|---|
| Original Completion Target | December 2025 |
| Revised Completion Target | March 2026 |
| Extension Period | 3 months |
| Additional Investment Required | Not Applicable |
Reasons for Schedule Revision
The delay in both pipeline sections has been attributed to similar operational challenges. GAIL cited delays in obtaining Right of Use (RoU) permissions and issues related to fisheries front availability as the primary reasons for the schedule revision. These regulatory and environmental clearance processes are critical for pipeline construction activities, particularly in areas with significant fishing activities.
Project Progress Status
Despite the delays in the final sections, both pipeline projects have achieved substantial completion rates. The Jagdishpur-Haldia-Bokaro-Dhamra Pipeline has completed approximately 98.37% of its authorized length in terms of pipeline laying, with 94.34% already commissioned for operations. The Dhamra-Haldia Pipeline has achieved 90.42% completion in pipeline laying with 62.50% commissioned.
Regulatory Compliance
This disclosure was made in compliance with Regulation 30 of SEBI (Listing Obligations and Disclosure Requirements) Regulations, 2015, which requires companies to inform stock exchanges about material events and information. The announcement continues from GAIL's previous communication dated April 09, 2025, providing updated information on the project timeline. The company has notified both the National Stock Exchange of India Limited and BSE Limited about this development, ensuring transparency with stakeholders and investors.