GAIL Revises Completion Schedule for Key Pipeline Sections to March 2026

2 min read     Updated on 03 Jan 2026, 04:53 PM
scanx
Reviewed by
Radhika SScanX News Team
Overview

GAIL (India) Limited has extended the completion schedule for two key pipeline sections from December 2025 to March 2026, as approved by the Board of Directors on January 03, 2026. The delay affects the Durgapur-Haldia section of the Jagdishpur-Haldia-Bokaro-Dhamra Pipeline and the Dhamra-Haldia Pipeline section, both facing challenges in obtaining Right of Use permissions and fisheries front availability. Despite these delays, both projects show significant progress with the main pipeline having 3,252 kilometers laid and 3,119 kilometers commissioned out of 3,306 kilometers authorized length.

28984981

*this image is generated using AI for illustrative purposes only.

GAIL (India) Limited has announced a three-month extension in the completion schedule for two key pipeline sections, moving the target date from December 2025 to March 2026. The revision was formally approved by the company's Board of Directors during their meeting held on January 03, 2026, which commenced at 02:00 p.m. and concluded at 04:30 p.m.

Pipeline Projects Overview

The revision affects two significant pipeline sections under GAIL's major infrastructure development program. Both projects represent critical components of India's natural gas distribution network and are part of the company's broader pipeline expansion strategy.

Pipeline Project Authorized Length Pipeline Laid Pipeline Commissioned Balance Section
Jagdishpur-Haldia-Bokaro-Dhamra 3,306 Kms 3,252 Kms 3,119 Kms Kolkata-Haldia Section
Dhamra-Haldia 240 Kms 217 Kms 150 Kms Dhamra-Haldia (West Bengal)

Completion Schedule Revision Details

The company has revised the completion timeline for both remaining sections due to operational challenges. The Durgapur-Haldia section of the Integrated Jagdishpur-Haldia-Bokaro-Dhamra Pipeline Project and the Dhamra-Haldia Pipeline section will now be completed by March 2026 instead of the originally planned December 2025.

Parameter Details
Original Completion Target December 2025
Revised Completion Target March 2026
Extension Period 3 months
Additional Investment Required Not Applicable

Reasons for Schedule Revision

The delay in both pipeline sections has been attributed to similar operational challenges. GAIL cited delays in obtaining Right of Use (RoU) permissions and issues related to fisheries front availability as the primary reasons for the schedule revision. These regulatory and environmental clearance processes are critical for pipeline construction activities, particularly in areas with significant fishing activities.

Project Progress Status

Despite the delays in the final sections, both pipeline projects have achieved substantial completion rates. The Jagdishpur-Haldia-Bokaro-Dhamra Pipeline has completed approximately 98.37% of its authorized length in terms of pipeline laying, with 94.34% already commissioned for operations. The Dhamra-Haldia Pipeline has achieved 90.42% completion in pipeline laying with 62.50% commissioned.

Regulatory Compliance

This disclosure was made in compliance with Regulation 30 of SEBI (Listing Obligations and Disclosure Requirements) Regulations, 2015, which requires companies to inform stock exchanges about material events and information. The announcement continues from GAIL's previous communication dated April 09, 2025, providing updated information on the project timeline. The company has notified both the National Stock Exchange of India Limited and BSE Limited about this development, ensuring transparency with stakeholders and investors.

Historical Stock Returns for GAIL

1 Day5 Days1 Month6 Months1 Year5 Years
-1.33%+1.19%-1.11%-9.28%-9.45%+102.80%

GAIL Revises KKBMPL Pipeline Project Completion Schedule to March 2026

1 min read     Updated on 03 Jan 2026, 04:52 PM
scanx
Reviewed by
Riya DScanX News Team
Overview

GAIL (India) Limited has revised the completion schedule for its Kochi-Koottanad-Bengaluru-Mangaluru Pipeline (KKBMPL) project from December 2025 to March 2026. The 1,104 km pipeline project has 884 km laid and 628 km commissioned, with balance work under construction. The revision was approved by the Board on January 03, 2026, citing delays in availability of hindrance-free fronts as the primary reason.

28984944

*this image is generated using AI for illustrative purposes only.

GAIL (India) Limited has announced a revision in the completion schedule for its major pipeline infrastructure project, extending the timeline due to construction challenges. The Maharatna company disclosed this development under Regulation 30 of SEBI LODR Regulations, 2015, following Board approval on January 03, 2026.

Project Details and Current Status

The Kochi-Koottanad-Bengaluru-Mangaluru Pipeline (KKBMPL) project represents a significant infrastructure development in India's gas distribution network. The project details and current progress are outlined below:

Parameter: Details
Pipeline Name: Kochi-Koottanad-Bengaluru-Mangaluru Pipeline (KKBMPL)
Authorized Length: 1,104 km
Pipeline Laid: 884 km
Pipeline Commissioned: 628 km
Remaining Construction: Balance work under construction

Schedule Revision Details

The company has revised the completion timeline for the remaining construction work on the KKBMPL project. The schedule adjustment reflects operational challenges encountered during the construction phase.

Timeline Aspect: Details
Original Completion: December 2025
Revised Completion: March 2026
Scope: Balance under construction
Additional Investment: Not Applicable
Primary Reason: Delay in availability of hindrance free fronts

Board Approval and Regulatory Compliance

The revision in completion schedule received formal approval from GAIL's Board of Directors during their meeting on January 03, 2026. The board meeting commenced at 02:00 p.m. and concluded at 04:30 p.m., where directors reviewed and approved the timeline adjustment.

The disclosure was made in compliance with SEBI (Listing Obligations and Disclosure Requirements) Regulations, 2015, ensuring transparency with stakeholders and regulatory authorities. The company has communicated this development to both the National Stock Exchange of India Limited and BSE Limited, where GAIL shares are listed under scrip codes GAIL-EQ and 532155 respectively.

Construction Challenges

The primary factor contributing to the schedule revision is the delay in availability of hindrance-free fronts for construction activities. This challenge is common in large-scale pipeline projects that traverse diverse geographical terrains and require coordination with multiple stakeholders for land access and clearances.

With 884 km of the total 1,104 km pipeline already laid and 628 km commissioned, the project has achieved substantial progress. The remaining construction work is now scheduled for completion by March 2026, representing a three-month extension from the original December 2025 timeline.

Historical Stock Returns for GAIL

1 Day5 Days1 Month6 Months1 Year5 Years
-1.33%+1.19%-1.11%-9.28%-9.45%+102.80%