GAIL Revises Srikakulam Angul Pipeline Project Completion Schedule to June 2026
GAIL (India) Limited has revised the completion schedule for its 744 km Srikakulam Angul Pipeline Project from December 2025 to June 2026. While the 422 km main pipeline was successfully commissioned on September 26, 2025, delays in forest working permissions for 56 km of the 322 km spur line have necessitated the timeline extension. The company has completed 280 km of the spur pipeline, with tree cutting operations currently in progress following sequential approval of permissions through September 2025. The revision was approved by the Board of Directors on January 03, 2026, with no additional investment required.

*this image is generated using AI for illustrative purposes only.
GAIL (India) Limited has announced a revision in the completion schedule for its Srikakulam Angul Pipeline Project, extending the timeline from December 2025 to June 2026. The announcement was made through a regulatory disclosure under Regulation 30 of SEBI LODR Regulations, 2015, following approval by the company's Board of Directors on January 03, 2026.
Project Overview
The Srikakulam Angul Pipeline Project represents a significant infrastructure development comprising a total length of 744 km. The project is structured in two main components: a 422 km main pipeline and a 322 km spur pipeline, designed to enhance the natural gas distribution network in the region.
| Component: | Length | Status |
|---|---|---|
| Main Pipeline: | 422 km | Commissioned on September 26, 2025 |
| Spur Pipeline: | 322 km | 280 km completed, 42 km pending |
| Total Project: | 744 km | Revised completion: June 2026 |
Completion Status and Challenges
The main pipeline component has achieved full operational status, with the entire 422 km length commissioned on September 26, 2025. However, progress on the spur line has encountered regulatory delays that necessitated the schedule revision.
For the 322 km spur pipeline, GAIL has successfully completed 280 km of construction. The remaining work has been impacted by delays in obtaining forest working permissions for a 56 km stretch of the pipeline route.
Regulatory Approval Timeline
The company faced sequential approval challenges that affected project execution:
- Forest working permissions were received progressively until June 23, 2025
- Tree cutting permissions followed sequentially through September 2025
- Tree cutting operations are currently in progress for the affected sections
These regulatory processes have directly contributed to the six-month extension in the project completion timeline.
Board Approval and Compliance
The schedule revision received formal approval from GAIL's Board of Directors during their meeting held on January 03, 2026. The meeting commenced at 2:00 PM and concluded at 4:30 PM, with the decision forming part of the company's compliance obligations under SEBI listing regulations.
The disclosure emphasizes that no additional investment is required for the revised completion schedule, indicating that the delay is primarily operational rather than financial in nature. This project revision reflects the complex regulatory environment surrounding infrastructure development in India, particularly for projects traversing forest areas that require multiple levels of environmental clearances.