ACME Solar commissions 53.63 MW BESS phase in Rajasthan
- ACME Solar commissions 53.63 MW BESS Phase-I in Rajasthan
- Part of larger 300 MW FDRE Project in Bikaner district
- Commercial operation date set for September 16, 2026
- Renewable energy generation component remains under development

*this image is generated using AI for illustrative purposes only.
ACME Solar Holdings has commissioned Phase-I of its Battery Energy Storage System (BESS) project in Rajasthan, marking a key milestone in its renewable energy infrastructure development.
The commissioning involves 53.63 MW/300 MWh of capacity, which forms part of the larger 300 MW / 1581 MWh FDRE Project located in Village Kelan, District Bikaner. The subsidiary ACME Greentech Seventh Private Limited executed the commissioning on September 14, 2026, with the Commercial Operation Date (COD) set for September 16, 2026.
Project Status
The company disclosed that only the BESS component has been commissioned at this stage. The corresponding renewable energy generation component remains under development. This phased approach allows for partial operationalization while construction continues on the broader solar infrastructure.
| Project Component | Capacity | Status |
|---|---|---|
| BESS Phase-I | 53.63 MW / 300 MWh | Commissioned |
| Total FDRE Project | 300 MW / 1581 MWh | Under Development |
The disclosure was made under Regulation 30 of the SEBI (Listing Obligations and Disclosure Requirements) Regulations, 2015, to both BSE and NSE.
Historical Stock Returns for ACME Solar Holdings
| 1 Day | 5 Days | 1 Month | 6 Months | 1 Year | 5 Years |
|---|---|---|---|---|---|
| +1.27% | +0.10% | +9.98% | +79.49% | +33.06% | 0.0% |
How will the commissioning of Phase-I BESS impact ACME Solar's revenue recognition and cash flow in the upcoming fiscal quarters?
What is the expected timeline for completing the remaining renewable energy generation component of the 300 MW FDRE project?
How does this phased BESS deployment position ACME Solar against competitors in India's rapidly growing energy storage market?