ACME Solar secures ₹1,571 crore IIFCL funding for Rajasthan project

scanx
Reviewed by
Anirudha BScanX News Team
Key Highlights
  • ACME Solar secured ₹1,571 crore from IIFCL for its 300 MW Rajasthan project
  • IIFCL acts as sole lender with a 19-year repayment tenor
  • Total fiscal financing reached ₹10,976 crore with ₹2,123 crore capex
  • Project includes 1,350 MWh BESS and 25-year PPA at ₹6.28/unit
  • Grid connectivity is operational with substation works in advanced stages
powered bylight_fuzz_icon
49345501

*this image is generated using AI for illustrative purposes only.

ACME Solar Holdings secured ₹1,571 crore in long-term project funding from India Infrastructure Finance Company Ltd (IIFCL) on August 27, 2026. The financing supports the construction of the ACME Renewtech Sixth 300 MW assured peak power project in Rajasthan.

This marks IIFCL's first sole greenfield finance to ACME Solar, with the lender acting as the sole financier. The loan carries a repayment tenor of 19 years and was secured at a competitive interest rate.

Project Structure and Financing

The funding brings ACME Solar's total financing secured during the current fiscal to ₹10,976 crore. The project involves a total capital expenditure of ₹2,123 crore.

Metric Value
Funding Amount ₹1,571 crore
Lender IIFCL (Sole Lender)
Tenor 19 years
Total Capex ₹2,123 crore
Fiscal Financing Secured ₹10,976 crore

The company executed a Power Purchase Agreement (PPA) with SECI Limited for a period of 25 years at a tariff of ₹6.28/unit.

Execution Status and Technology

The project integrates solar generation with a 1,350 MWh Battery Energy Storage System (BESS). This hybrid model ensures higher predictability and dispatchability to meet supply obligations under the PPA.

Execution is progressing with grid connectivity already operational. The pooling substation and dedicated transmission line are in advanced stages of completion, while land for the site is substantially secured.

What the Numbers Show

The project represents a significant portion of ACME Solar's battery-storage capital deployment programme for the financial year. With a total capex of ₹2,123 crore and secured funding of ₹1,571 crore, the project demonstrates strong bankability for hybrid renewable assets. The long-term 25-year PPA structure provides revenue visibility, while the sole-lender arrangement with IIFCL simplifies the debt servicing framework for this specific asset.

Portfolio Context

ACME Solar operates a diversified portfolio of 8,370 MW spanning solar, wind, storage, FDRE, and hybrid solutions. The company has an operational contracted capacity of 2,990 MW and approximately 3.62 GWh of BESS capacity.

Under construction, the company holds a contracted capacity of 5,380 MW, with an under-construction PPA signed portfolio standing at 4,010 MW. The firm utilizes an in-house EPC and O&M division for end-to-end development.

Historical Stock Returns for ACME Solar Holdings

1 Day5 Days1 Month6 Months1 Year5 Years
0.0%+4.06%+8.20%+68.50%+38.55%0.0%

How might the success of this sole-lender model with IIFCL influence future financing structures for other hybrid renewable projects in India?

What are the projected operational cost advantages of integrating 1,350 MWh of BESS into the 300 MW solar project compared to standalone solar assets?

Given the ₹6.28/unit tariff, how does this project's revenue stability compare to recent trends in Indian solar PPA pricing?

Acme Solar signs 25-year, 130 MW renewable deal with Northeast Frontier Railway

scanx
Reviewed by
Suketu GScanX News Team
Key Highlights
  • Acme Solar Holdings signed a 25-year power supply agreement with Northeast Frontier Railway
  • The project has a capacity of 130 MW under a renewable energy framework
  • The agreed tariff is ₹4.35 per kWh for the full contract duration
  • Energy supply under the agreement is scheduled to commence on February 25, 2029
powered bylight_fuzz_icon
49262316

*this image is generated using AI for illustrative purposes only.

Acme Solar Holdings has signed a 25-year power supply agreement with Northeast Frontier Railway for a 130 MW renewable energy project at a tariff of ₹4.35 per kWh, with supply commencing on February 25, 2029.

Deal at a glance

The agreement marks a long-term commitment between Acme Solar Holdings and Northeast Frontier Railway for clean energy supply. The key terms of the deal are outlined below.

Parameter Details
Counterparty Northeast Frontier Railway
Project capacity 130 MW
Agreement duration 25 years
Tariff ₹4.35 per kWh
Supply commencement date February 25, 2029

The 25-year tenure underscores the long-term nature of the energy supply arrangement, with a fixed tariff of ₹4.35 per kWh locked in for the duration of the contract.

Historical Stock Returns for ACME Solar Holdings

1 Day5 Days1 Month6 Months1 Year5 Years
0.0%+4.06%+8.20%+68.50%+38.55%0.0%

How does the locked-in tariff of ₹4.35 per kWh compare to current market rates for renewable energy, and what is the risk of this rate becoming uncompetitive by 2029?

What specific financing strategies or capital expenditure plans has Acme Solar Holdings outlined to fund the construction of the 130 MW project before the 2029 commencement date?

Could this agreement with Northeast Frontier Railway signal a broader trend of Indian Railways accelerating its procurement of large-scale renewable energy contracts?

More News on ACME Solar Holdings

1 Year Returns:+38.55%