NTPC Green Energy Limited has commissioned 300 MW capacity of its Bhadla Solar PV Project in Phalodi, Rajasthan, which began commercial operations on January 13, 2026. This represents the first phase of a 500 MW project operated by NTPC Renewable Energy Limited. The addition increases the company's total installed capacity from 8,010.28 MW to 8,310.28 MW, strengthening its renewable energy portfolio.

*this image is generated using AI for illustrative purposes only.
NTPC Green Energy Limited has achieved a significant milestone with the successful commissioning of the first phase of its Bhadla Solar PV Project in Rajasthan. The company announced that 300 MW capacity out of the total 500 MW project has commenced commercial operations, marking another step forward in India's renewable energy expansion.
Project Details and Commissioning
The commissioned solar capacity is part of the larger Bhadla Solar PV Project located in Phalodi, Rajasthan. The project is operated by NTPC Renewable Energy Limited, a wholly owned subsidiary of NTPC Green Energy Limited.
| Parameter: | Details |
|---|---|
| Commissioned Capacity: | 300 MW |
| Total Project Capacity: | 500 MW |
| Location: | Phalodi, Rajasthan |
| Commercial Operation Date: | January 13, 2026 |
| Certification Date: | January 14, 2026 |
| Certifying Authorities: | SECI & RRECL |
Capacity Enhancement Impact
The addition of this 300 MW solar capacity has substantially increased the company's operational portfolio. The commissioning represents a strategic expansion of NTPC Green Energy Limited's renewable energy footprint across India.
| Capacity Metrics: | MW |
|---|---|
| Previous Commercial Capacity: | 8,010.28 MW |
| Newly Added Capacity: | 300.00 MW |
| Total Installed Capacity: | 8,310.28 MW |
Regulatory Compliance
The company made this announcement in compliance with Regulation 30 of the SEBI (Listing Obligations and Disclosure Requirements) Regulations, 2015. The disclosure was filed on January 14, 2026, ensuring transparency with stakeholders and regulatory authorities.
The certification process involved both the Solar Energy Corporation of India (SECI) and Rajasthan Renewable Energy Corporation Limited (RRECL), confirming the project meets all technical and operational standards required for commercial operation.
Strategic Significance
This commissioning represents the first phase of the Bhadla Solar PV Project, with the remaining 200 MW capacity expected to be commissioned in subsequent phases. The project strengthens NTPC Green Energy Limited's position in India's renewable energy sector and contributes to the country's clean energy objectives.
The Bhadla Solar Park in Rajasthan is one of India's largest solar installations, and NTPC Green Energy Limited's participation underscores its commitment to large-scale renewable energy development. The successful commissioning of this phase demonstrates the company's execution capabilities in utility-scale solar projects.