Coal India commissions 200 MW solar capacity at Khavda, Gujarat
Coal India commissioned 200 MW of its 300 MW solar power project at Khavda, Gujarat, on July 15, 2026, following the receipt of a commissioning certificate from the Gujarat Energy Development Agency (GEDA). The remaining 100 MW of the project is pending commissioning.

*this image is generated using AI for illustrative purposes only.
Coal India has commissioned 200 MW of its 300 MW solar power project at Khavda, Gujarat, receiving the commissioning certificate from Gujarat Energy Development Agency (GEDA) on July 15, 2026. This development marks a significant step in the company's renewable energy strategy, utilizing the Khavda region's established infrastructure for large-scale power generation.
Project Overview
The Khavda Solar Project represents Coal India's expansion into green energy. The following table summarises the key details of the project:
| Parameter | Details |
|---|---|
| Project Name | Khavda Solar Project |
| Location | Khavda, Gujarat |
| Total Project Capacity | 300 MW |
| Capacity Commissioned | 200 MW |
| Capacity Pending Commissioning | 100 MW |
| Commissioning Certificate Date | July 15, 2026 |
| Issuing Authority | Gujarat Energy Development Agency (GEDA) |
Commissioning Milestone
With 200 MW now operational, Coal India has brought a substantial portion of the project online. The remaining 100 MW of the total project capacity is yet to be commissioned. The disclosure was made to the exchanges in compliance with Regulation 30 of the SEBI (Listing Obligations and Disclosure Requirements) Regulations, 2015.
Historical Stock Returns for Coal India
| 1 Day | 5 Days | 1 Month | 6 Months | 1 Year | 5 Years |
|---|---|---|---|---|---|
| -0.66% | -0.51% | -4.59% | +3.47% | +10.75% | +196.06% |
What is the expected timeline for the commissioning of the remaining 100 MW capacity?
How will the operationalization of this solar project impact Coal India's overall renewable energy targets?
What are the projected financial returns or cost savings from the Khavda Solar Project once fully operational?