NTPC group capacity rises to 90,954 MW on Vanki wind project COD
NTPC Limited's group installed capacity rose to 90,954 MW and commercial capacity to 89,874 MW after the 50.4 MW Vanki Wind Energy Project in Gujarat began operations on July 8, 2026. NTPC Green Energy Limited's commercial capacity will increase to 10,721.80 MW with this addition.

*this image is generated using AI for illustrative purposes only.
NTPC Limited has increased its group's total installed capacity to 90,954 MW and commercial capacity to 89,874 MW following the declaration of commercial operation of the Vanki Wind Energy Project. The first part capacity of 50.4 MW, located in Nakhatrana, Kutch, Gujarat, was commissioned by NTPC Renewable Energy Limited, a wholly owned subsidiary of NTPC Green Energy Limited, effective July 8, 2026. This development strengthens the group's renewable energy footprint.
NTPC Green Energy Limited (NGEL) disclosed the commercial operation pursuant to Regulation 30 of the SEBI (Listing Obligations and Disclosure Requirements) Regulations, 2015. The filing was signed by Deepak Charuvil Sankunni, Company Secretary & Compliance Officer of NGEL. With this addition, the commercial capacity of the NTPC Green Energy Limited group stands at 10,671.40 MW and will increase to 10,721.80 MW.
Project Details
The following table outlines the commissioning details for the Vanki Wind Energy Project:
| Project Part | Capacity (MW) | Commercial Operation Date |
|---|---|---|
| First Part | 50.4 MW | July 8, 2026 |
| Total Capacity | 50.4 MW |
Separately, NTPC Limited had previously commissioned the Bhilai Floating Solar Power Station, developed by joint venture NTPC-SAIL Power Company Limited (NSPCL). The 15 MW project was fully commissioned on June 24, 2026, with the final 5 MW module becoming operational. Additionally, the final 41.6 MW unit of the 176 MW Solar PV Project at Ramagundam, Telangana, was declared on commercial operation on June 30, 2026.
Historical Stock Returns for NTPC
| 1 Day | 5 Days | 1 Month | 6 Months | 1 Year | 5 Years |
|---|---|---|---|---|---|
| 0.0% | -1.25% | -1.08% | -0.58% | +0.69% | +186.24% |
How will the commissioning of the Vanki Wind Energy Project impact NTPC's timeline for achieving its non-fossil fuel capacity targets?
What is the projected capital expenditure for the remaining phases of the Vanki Wind Energy Project and other upcoming renewable ventures?
How will the increased renewable capacity affect NTPC's overall blended power tariff and profit margins in the coming fiscal year?