PNC Infratech Subsidiary Receives Provisional Completion Certificate for HAM Highway Project on NH-731A in Uttar Pradesh
PNC Infratech Limited announced that its subsidiary, Prayagraj Kaushambi Highway Package 3 Private Limited, received a Provisional Completion Certificate (PCC/PCOD) dated 8th May 2026 for the construction of a 4-lane highway on NH-731A (Singraur Uphar to Baranpur Kadipur Ichauli) in Uttar Pradesh under the Hybrid Annuity Mode. The project, with a Bid Project Cost of Rs. 819.0 Crores, achieved provisional completion on 31st March 2026, within the 90-day grace period from the Scheduled Completion Date of 31.01.2026.

*this image is generated using AI for illustrative purposes only.
PNC Infratech Limited has announced that its subsidiary, Prayagraj Kaushambi Highway Package 3 Private Limited, has been issued a Provisional Completion Certificate (PCC/PCOD) for a Hybrid Annuity Mode (HAM) highway project in the state of Uttar Pradesh. The certificate, dated 8th May 2026, was issued by the Independent Engineer, declaring the project fit for entry into commercial operations with effect from 31st March 2026.
Project Overview
The project involves the construction of a 4-lane highway from Km 49.155 to Km 74.700 (Singraur Uphar to Baranpur Kadipur Ichauli) of NH-731A with paved shoulders (including Ganga Bridge) in Uttar Pradesh, executed under the Hybrid Annuity Mode as Package-III. The concessionaire for the project is Prayagraj Kaushambi Highway Package 3 Private Limited, a subsidiary of PNC Infratech Limited, with the authority being the Ministry of Road Transport & Highways (MoRT&H) acting through the Uttar Pradesh Public Works Department (UPPWD).
Key Project Details
The following table summarises the key parameters of the completed project as disclosed by the company:
| Parameter: | Details |
|---|---|
| Concessionaire: | Prayagraj Kaushambi Highway Package 3 Private Limited |
| Authority: | Ministry of Road Transport & Highways (MoRT&H) acting through Uttar Pradesh Public Works Department (UPPWD) |
| Nature of Contract: | Construction of 4-lane highway from Km 49.155 to Km 74.700 (Singraur Uphar to Baranpur Kadipur Ichauli) of NH-731A with paved shoulders (i/c Ganga Bridge) in Uttar Pradesh on Hybrid Annuity Mode (Package-III) |
| Contract Mode: | Hybrid Annuity Mode (HAM) |
| Appointed Date: | 01.02.2024 (Completion Period: 730 Days) |
| Scheduled Completion Date: | 31.01.2026 |
| Provisional Completion Date: | 31.03.2026 (achieved within the 90-day grace period from the Scheduled Completion Date) |
| Bid Project Cost: | Rs. 819.0 Crores (plus Price Index Multiple amount as per the Concession Agreement) |
| Amendments/Terminations: | NA |
Provisional Completion and Commercial Operations
The Provisional Completion Date of 31st March 2026 was achieved within the 90-day grace period from the Scheduled Completion Date of 31.01.2026. The Independent Engineer issued the PCC/PCOD via e-mail dated 8th May 2026, formally certifying the project's readiness for commercial operations. The disclosure was made in accordance with SEBI (Listing Obligations and Disclosure Requirements) Regulations, 2015, and pursuant to SEBI Circular No. SEBI/HO/49/14/14(7)2025-CFD-POD2/1/3762/2026 dated January 30, 2026.
The project, with a Bid Project Cost of Rs. 819.0 Crores (plus Price Index Multiple amount as per the Concession Agreement), represents a significant infrastructure milestone for PNC Infratech and its subsidiary in the highway development sector in Uttar Pradesh.
Historical Stock Returns for PNC Infratech
| 1 Day | 5 Days | 1 Month | 6 Months | 1 Year | 5 Years |
|---|---|---|---|---|---|
| +0.42% | +5.06% | +30.84% | -19.02% | -10.12% | +1.19% |
How will the annuity payments from this HAM project impact PNC Infratech's revenue visibility and cash flow over the concession period?
What is the timeline for PNC Infratech to receive the remaining construction payment tranches now that commercial operations have commenced?
Does PNC Infratech have additional HAM projects in Uttar Pradesh in its pipeline, and how might this completion strengthen its positioning for future NHAI bids?