Juniper Green Energy commissions final 5 MW of 150 MW hybrid project
- Juniper Green Energy Limited fully commissioned its 150 MW Wind Solar Hybrid Project on October 12, 2026.
- The final 5 MW wind turbine was installed, completing the project under a PPA with Gujarat Urja Vikas Nigam Limited.
- Aggregate operational renewable capacity now stands at ~2,745 MWp, alongside ~603 MWh of BESS capacity.
- Commissioning was confirmed by Gujarat Energy Development Agency and Paschim Gujarat Vij Company Limited officials.

*this image is generated using AI for illustrative purposes only.
Juniper Green Energy Limited has fully commissioned its 150 MW Wind Solar Hybrid Power Project with the commissioning of the final 5 MW wind turbine on October 12, 2026. This completion marks the full operational status of the project under a Power Purchase Agreement with Gujarat Urja Vikas Nigam Limited.
The commissioning was witnessed and confirmed by officials from the Gujarat Energy Development Agency and Paschim Gujarat Vij Company Limited. A formal certificate confirming the commissioning is expected to be issued shortly.
Operational Capacity Update
With this latest addition, the aggregate operational capacity of Juniper Green Energy and its subsidiaries stands at ~2,745 MWp of renewable energy generation capacity. The company also reports an operational Battery Energy Storage System (BESS) capacity of ~603 MWh.
| Metric | Capacity |
|---|---|
| Total Operational Renewable Capacity | ~2,745 MWp |
| Total Operational BESS Capacity | ~603 MWh |
| Newly Commissioned Wind Capacity | 5 MW |
| Total Project Size (Wind Solar Hybrid) | 150 MW |
The completion of this specific 150 MW project follows earlier intimations provided by the company on September 10, 2026, and September 11, 2026, regarding the phased commissioning of additional capacity. The final turbine installation completes the project's scope as contracted.
Historical Stock Returns for Juniper Green Energy
| 1 Day | 5 Days | 1 Month | 6 Months | 1 Year | 5 Years |
|---|---|---|---|---|---|
| -1.13% | +1.45% | +4.47% | +20.96% | +20.96% | +20.96% |
How will the full commissioning of the 150 MW project impact Juniper Green Energy's quarterly revenue recognition under the Gujarat Urja Vikas Nigam Limited Power Purchase Agreement?
What are the company's specific pipeline targets for expanding its ~2,745 MWp renewable capacity and ~603 MWh BESS capacity in the next fiscal year?
How does the integration of Battery Energy Storage Systems with wind-solar hybrids position Juniper Green Energy to capitalize on upcoming grid balancing mandates in Gujarat?