Ceigall India Receives Completion Certificate for Delhi-Amritsar-Katra Expressway Package-07
Ceigall India Limited received a Completion Certificate on 5th May 2026 for a 35.15 KM stretch of the Delhi-Amritsar-Katra Expressway (Package-07) in Punjab, with the completion date recorded as 26th February 2026. The project, executed on EPC mode under Bharatmala Pariyojna, carries a Bid Project Cost of Rs. 881.00 Crore and was awarded on 20th July 2021. The certificate was issued pursuant to Article 12 of the EPC Contract Agreement by the Authority's Engineer, excluding the De-linking Part of the Work. The disclosure was made to stock exchanges on 6th May 2026 under Regulation 30 of SEBI (LODR) Regulations, 2015.

*this image is generated using AI for illustrative purposes only.
Ceigall India Limited has received a Completion Certificate pursuant to Article 12 of the EPC Contract Agreement for its Package-07 project on the four-lane Greenfield Delhi-Amritsar-Katra Expressway in Punjab. The certificate was issued by the Authority's Engineer on 5th May 2026 and was disclosed to the stock exchanges on 6th May 2026 under Regulation 30 of the SEBI (Listing Obligations and Disclosure Requirements) Regulations, 2015.
Project Completion Details
The Completion Certificate certifies that all works forming part of the Project Highway have been completed over a stretch of 35.15 KM on 26th February 2026, except for the De-linking Part of the Work. The project involves the construction of a four-lane Greenfield expressway from the Junction with Patiala-Bathinda Road (NH-07) near Bhawanigarh to the Junction with Ludhiana-Malerkotla Road (SH-11) near Bhogiwal village (Km 188+830 to Km 225+770), executed on EPC mode under Bharatmala Pariyojna in the state of Punjab.
The key project parameters are summarised below:
| Parameter: | Details |
|---|---|
| Project Name: | Delhi-Amritsar-Katra Expressway (Package-07) |
| Stretch: | Km 188+830 to Km 225+770, Punjab |
| Length Completed: | 35.15 KM |
| Bid Project Cost: | Rs. 881.00 Crore |
| Date of Award: | 20.07.2021 |
| Estimated Date of Completion (with authorised extension): | 01.10.2025 |
| Date of Completion: | 26.02.2026 |
| Authority: | NHAI |
| Mode: | EPC under Bharatmala Pariyojna |
Broader Project Portfolio Context
This project forms part of Ceigall India's ongoing infrastructure portfolio as referenced in its Red Herring Prospectus. The company is engaged in multiple highway and infrastructure projects across several states. A selection of other projects undertaken by the company includes:
| S. No. | Project | State | Bid Project Cost (₹ million) | Date of Award | Authority |
|---|---|---|---|---|---|
| 2. | Delhi-Saharanpur Highway (Ch. 14.750 to 31.600) – Six Lane | Uttar Pradesh | 13,235.20 | April 16, 2022 | NHAI |
| 3. | Amritsar Connectivity – Four-Lane Greenfield (Km 40+900 to Km 70+950) | Punjab | 10,710.00 | May 12, 2021 | NHAI |
| 4. | Ludhiana–Rupnagar NH-205K – Four/Six Lane Greenfield (43.26 Km) | Punjab | 10,382.40 | June 2, 2022 | IRCON |
| 6. | Ramban-Banihal PKG II | J&K | 8,460.00 | September 3, 2021 | NHAI |
| 7. | Mansi-Fungo Halt-Simri Bakhtiyarpur Section (SH-95) | Bihar | 7,816.50 | September 8, 2023 | BSRDCL |
| 8. | Ramban-Banihal PKG III – Four Laning | J&K | 3,690.00 | September 2, 2021 | NHAI |
| 9. | Re-Surfacing of Runway and Aircraft Operating Area at AF Station Halwara | Punjab | 1,384.06 | June 13, 2023 | MES |
| 11. | Gonde-Vadape Project – 6 Lane Grade Separated Structures, NH-3 | Maharashtra | 811.33 | November 23, 2020 | NHAI |
Regulatory Disclosure
The disclosure was made by Company Secretary and Compliance Officer Megha Kainth (Membership No.: F7639) on behalf of Ceigall India Limited. The company has requested the stock exchanges to take the information on record. The project's details are referenced on pages 217 and 218 of the company's Red Herring Prospectus.
Historical Stock Returns for Ceigall India
| 1 Day | 5 Days | 1 Month | 6 Months | 1 Year | 5 Years |
|---|---|---|---|---|---|
| +6.13% | +8.28% | +30.67% | +48.06% | +39.25% | -5.33% |
How will the delayed completion of Package-07 (nearly 5 months beyond the authorized extension deadline) impact Ceigall India's eligibility for future NHAI bids or its penalty clauses under the EPC contract?
What is the status and expected timeline for the remaining 'De-linking Part of the Work' excluded from the Completion Certificate, and could it affect final payment settlements?
Given Ceigall India's concentration of projects in Punjab and J&K, how might the company's order book diversification strategy evolve as the Delhi-Amritsar-Katra Expressway nears full completion?