Antony Waste Handling Cell Q2FY27 Results: Tonnage up 0.8% YoY
- Total tonnage managed grew 0.8% YoY to 1.28 million tonnes in Q2FY27
- Collection and Transportation volumes rose 11.5% YoY to 0.60 million tonnes
- Processing volumes declined 7.2% YoY due to PCMC WtE facility suspension
- Core revenue remained stable with a 1% YoY decline, offset by 12% C&T growth
- PCMC WtE facility expected to resume operations by December 2026

*this image is generated using AI for illustrative purposes only.
Antony Waste Handling Cell managed 1.28 million tonnes of waste in Q2FY27, marking a 0.8% year-on-year (YoY) increase. This growth occurred despite the temporary suspension of energy operations at the Pimpri Chinchwad (PCMC) Waste-to-Energy (WtE) facility due to structural damage from monsoon rainfall.
Collection and Transportation (C&T) volumes expanded 11.5% YoY to 0.60 million tonnes. The surge was driven by the ramp-up of new operations awarded by the Brihanmumbai Municipal Corporation (BMC) and higher volumes in Navi Mumbai, Panvel, and Noida. Conversely, processing volumes fell 7.2% YoY to 0.68 million tonnes, primarily attributed to the halt in WtE activities at PCMC.
Core revenue remained broadly stable, declining slightly by 1% YoY. The absence of power sales from the PCMC facility was largely offset by a 12% YoY rise in C&T revenue. Excluding power sales from the base quarter, core revenue grew 2% YoY, highlighting the resilience of the contract portfolio. For H1FY27, total tonnage reached 2.71 million tonnes, reflecting 4.5% growth.
Operational Metrics Overview
| Metric | Q2FY27 | Change (YoY) | Notes |
|---|---|---|---|
| Total Tonnage Managed | 1.28 million tonnes | +0.8% | Resilient growth despite disruptions |
| C&T Volumes | 0.60 million tonnes | +11.5% | Driven by BMC and other municipal contracts |
| Processing Volumes | 0.68 million tonnes | -7.2% | Impacted by PCMC WtE suspension |
| RDF Sold | 49,000 tonnes | +23% | Significant volume expansion |
| Compost Sold | 2,000 tonnes | -38% | Seasonal demand dip and operational disruption |
PCMC Facility Status and Restoration
The PCMC WtE facility, operated by material subsidiary Antony Lara Renewable Energy Private Limited, remains offline following an incident on July 8, 2026. Excessive monsoon rainfall caused a legacy waste landfill adjacent to the site to collapse, resulting in severe structural damage and tragic loss of life. No power was generated during the quarter, compared to 14.0 million units in Q2FY26.
Restoration efforts are underway in coordination with PCMC authorities. Original Equipment Manufacturers (OEMs) are inspecting and repairing affected systems. The facility is expected to be functional by December 2026. Interim operations, including Material Recovery Facility (MRF) and composting, resumed and processed 33,600 tonnes of waste during the quarter.
What the Numbers Show
The divergence between 11.5% growth in C&T volumes and 7.2% decline in processing volumes underscores a strategic shift in revenue composition. While the loss of power generation capacity temporarily suppresses high-margin energy revenue, the robust performance in C&T segments demonstrates effective contract diversification. Additionally, the 23% rise in Refuse Derived Fuel (RDF) sales partially mitigates the impact of the 38% drop in compost sales, indicating adaptive product mix management amidst seasonal and operational constraints.
Historical Stock Returns for Antony Waste Handling Cell
| 1 Day | 5 Days | 1 Month | 6 Months | 1 Year | 5 Years |
|---|---|---|---|---|---|
| -0.25% | -1.89% | -6.00% | -35.00% | -35.96% | 0.0% |
How will the anticipated December 2026 restoration of the PCMC WtE facility impact Antony Waste's EBITDA margins and power sales revenue in Q3FY27?
What are the long-term implications of the shift toward Collection & Transportation revenue for the company's overall profit margin profile compared to high-margin energy generation?
Could the structural failure at the PCMC site trigger stricter regulatory compliance costs or insurance adjustments for other waste-to-energy projects in monsoon-prone regions?