Khoobsurat Ltd Provides Brewery Project Installation and Commercial Production Timeline Updates
Khoobsurat Ltd has announced significant progress on its brewery project with brew-house and fermentation tank installations expected to complete by March 15, 2026. The bottling plant delivery is scheduled for end of March 2026, followed by technical integration with German expert support. The company anticipates brewing its first test batch between mid to end of April 2026, with commercial production commencing by mid-April 2026.

*this image is generated using AI for illustrative purposes only.
Khoobsurat Ltd has issued an important update to stakeholders regarding the progress of its brewery project under Regulation 30. The company has outlined a detailed timeline for equipment installation, testing phases, and the commencement of commercial beer production.
Equipment Installation Progress
The brewery project is advancing according to schedule with multiple critical components under installation. The company has provided specific timelines for key equipment deployment and operational readiness.
| Equipment Component | Timeline | Status |
|---|---|---|
| Brew-house Installation | By March 15, 2026 | Under Process |
| Fermentation Tanks | By March 15, 2026 | Under Process |
| Bottling Plant Delivery | End of March 2026 | Awaiting Delivery |
Technical Integration and Testing Phase
Following equipment delivery, Khoobsurat Ltd has outlined a comprehensive integration process involving technical expertise from Germany. The company expects to begin test production once all systems are properly connected and operational.
Key aspects of the integration phase include:
- Technical team from Germany visiting the plant in March 2026
- Integration of tanks and packaging plant by specialized technicians
- First test batch brewing scheduled between mid to end of April 2026
- Bottling plant operationalization and brewery production connectivity
Commercial Production Timeline
The company has established a clear pathway to commercial production, contingent upon successful completion of installation and testing phases. Commercial production readiness depends on the bottling plant becoming fully operative and connected to the brewery production system.
| Milestone | Expected Timeline |
|---|---|
| Technical Team Visit | March 2026 |
| First Test Batch | Mid to End April 2026 |
| Commercial Production Start | Mid-April 2026 |
The announcement, signed by Managing Director Sanjay Mishra, emphasizes the company's commitment to keeping stakeholders informed about this significant business development. The brewery project represents a major expansion initiative for Khoobsurat Ltd as it ventures into beer production and manufacturing.