L&T Wins Major Mumbai Metro Line 4 Electrification Order

2 min read     Updated on 24 Dec 2025, 10:21 AM
scanx
Reviewed by
Naman SScanX News Team
Overview

Larsen & Toubro's Transportation Infrastructure business has been awarded a significant contract by the Mumbai Metropolitan Region Development Authority (MMRDA) for the electrification of the 24.72 km Mumbai Metro Line 4 corridor. The project, designated as Package CA-298, includes electrification of 22 elevated stations between Bhakti Park (Wadala) and Cadbury junction. The scope encompasses design, supply, installation, and commissioning of power supply and traction systems, as well as SCADA implementation for the entire Metro line 4&4A covering 32 stations. This marks L&T's third consecutive order in the Line-4&4A corridor, following previous contracts for rolling stock, signaling, and track works.

28097499

*this image is generated using AI for illustrative purposes only.

Larsen & Toubro 's Transportation Infrastructure business has secured a significant order from the Mumbai Metropolitan Region Development Authority (MMRDA) for the electrification of the 24.72 km Mumbai Metro Line 4 corridor with 22 elevated stations.

Project Scope and Specifications

The comprehensive project involves the electrification of a 24.72 km long corridor running between Bhakti Park (Wadala) to Cadbury junction, serving 22 elevated stations. The contract, designated as Package CA-298, includes multiple technical components and infrastructure development activities.

Project Component Details
Route Length 24.72 km
Number of Stations 22 elevated stations
Corridor Bhakti Park (Wadala) to Cadbury junction
Package Code CA-298
Awarding Authority Mumbai Metropolitan Region Development Authority (MMRDA)

Technical Deliverables

The project scope encompasses design, manufacture, supply, installation, integration, testing and commissioning of power supply and traction systems for the 24.72 route km. Additionally, L&T will provide SCADA system for complete Metro line 4&4A covering 32 stations, depots and receiving substation.

The comprehensive scope also includes:

  • Electrical and mechanical works for the entire corridor
  • Lift and escalators for 22 elevated stations and 2 depots
  • Five years of comprehensive maintenance services
  • In-house design and execution by L&T's specialized team

Strategic Position in Mumbai Metro Corridor

This contract represents the third successive order that L&T has secured in the Line-4&4A corridor of Mumbai Metro, demonstrating the company's strong market position in urban transportation infrastructure. The company had previously won Package CA-234, which involved rolling stock, Communications-Based Train Control (CBTC) signalling, telecommunications, platform screen doors and depot machinery & plant for the entire corridor.

Previous Orders Scope
Package CA-234 Rolling stock, CBTC signalling, telecommunications, platform screen doors, depot machinery
Package CA-168 19.5 km ballast-less track-works across 15 stations
Package CA-298 Electrification, power supply, traction systems, SCADA

L&T had also secured another order for Package CA-168, involving 19.5 km ballast-less track-works across 15 stations, further consolidating its presence in this critical urban transportation project.

Company Background

Larsen & Toubro operates as a USD 30.00 billion Indian multinational engaged in EPC Projects, Hi-Tech Manufacturing, and Services across multiple geographies. The company has maintained leadership in its major lines of business for eight decades through a strong, customer-focused approach and constant pursuit of top-class quality standards.

Historical Stock Returns for Larsen & Toubro

1 Day5 Days1 Month6 Months1 Year5 Years
-0.16%-0.37%+0.85%+12.28%+11.20%+220.65%
Larsen & Toubro
View in Depthredirect
like15
dislike

L&T Wins Major LLDPE/HDPE Project from BPCL

2 min read     Updated on 23 Dec 2025, 09:56 AM
scanx
Reviewed by
Radhika SScanX News Team
Overview

Larsen & Toubro's Hydrocarbon Onshore business has secured a significant order from BPCL for the engineering, procurement, construction, and commissioning of India's largest LLDPE/HDPE Swing Unit in Bina, Madhya Pradesh. The project includes two trains with a combined capacity of 1150 KTPA, forming part of BPCL's Bina Petrochemicals Refinery Expansion Project. This aligns with India's Aatmanirbhar Bharat vision, aiming to enhance domestic manufacturing capabilities and reduce polymer import dependence.

28009604

*this image is generated using AI for illustrative purposes only.

Larsen & Toubro 's Hydrocarbon Onshore business secures major order from BPCL for engineering, procurement, construction and commissioning of India's largest LLDPE/HDPE Swing Unit at Bina, Madhya Pradesh.

Project Overview

The comprehensive project involves engineering, procurement, construction and commissioning of a Linear Low-Density Polyethylene/High-Density Polyethylene (LLDPE/HDPE) Swing Unit at Bina in Madhya Pradesh. The facility will comprise two trains with a combined capacity that positions it as India's largest LLDPE/HDPE Swing Unit.

Parameter Details
Project Type LLDPE/HDPE Swing Unit
Capacity Two trains of 575 KTPA each
Location Bina, Madhya Pradesh
Execution Model Lump Sum Turnkey basis
Significance India's largest LLDPE/HDPE Swing Unit

Strategic Importance

This project forms an integral part of BPCL's Bina Petrochemicals Refinery Expansion Project, which aims to establish a petrochemical complex and enhance refinery capacity from 7.8 MMTPA to 11 MMTPA. The initiative aligns with the Government of India's Aatmanirbhar Bharat vision by strengthening domestic manufacturing capabilities and achieving self-sufficiency in polymer production.

The project will set a new benchmark in polyethylene production capacity, contributing significantly to India's petrochemical manufacturing landscape and reducing dependence on imports.

Management Commentary

Subramanian Sarma, Deputy Managing Director & President-L&T, emphasized the order's significance: "This is a major order that will not only strengthen our balance sheet but also provide impetus to our demonstrated credentials in downstream hydrocarbon EPC space."

E S Sathyanarayanan, Senior Vice President & Head of L&T Energy Hydrocarbon-Onshore, highlighted the company's commitment: "In the ever-evolving landscape of the hydrocarbon and petrochemicals sector, this win for L&T Onshore is a testament to the trust that customers repose in our execution and delivering capabilities. We are fully committed to delivering the project with high standards of HSE and quality."

Business Vertical Capabilities

L&T Onshore operates as one of India's largest EPC businesses, delivering comprehensive Lump Sum Turnkey solutions across multiple sectors:

  • Upstream, midstream and downstream hydrocarbon sectors
  • Refinery expansions and petrochemical complexes
  • Gas processing plants and fertiliser plants
  • LNG terminals and cross-country pipelines

The business vertical maintains a strong execution track record across various geographies, demonstrating its capability to handle complex industrial projects.

Company Background

Larsen & Toubro is a USD 30.00 billion Indian multinational engaged in EPC Projects, Hi-Tech Manufacturing, and Services, operating across multiple geographies. The company has maintained leadership in its major lines of business for eight decades through a strong, customer-focused approach and constant quest for top-class quality.

Historical Stock Returns for Larsen & Toubro

1 Day5 Days1 Month6 Months1 Year5 Years
-0.16%-0.37%+0.85%+12.28%+11.20%+220.65%
Larsen & Toubro
View in Depthredirect
like16
dislike
More News on Larsen & Toubro
Explore Other Articles
4,047.30
-6.30
(-0.16%)