JSW Energy Powers Up: First Unit of Kutehr Hydro Plant Commissioned, Boosting Renewable Portfolio
JSW Energy has commissioned the first 80 MW unit of its 240 MW Kutehr Hydroelectric Power Plant in Himachal Pradesh. The project has a 35-year Power Purchase Agreement with Haryana Power Purchase Centre. This addition increases JSW Energy's renewable capacity to 56% of its portfolio. The company aims to reach 30 GW generation capacity and 40 GWh energy storage capacity by FY 2030.

*this image is generated using AI for illustrative purposes only.
JSW Energy Limited , a leading player in India's power sector, has achieved a significant milestone in its renewable energy expansion strategy. The company has successfully commissioned the first 80 MW unit of its 240 MW Kutehr Hydroelectric Power Plant in Himachal Pradesh's Chamba district, marking a crucial step in its commitment to clean energy.
Project Highlights
- Location: Chamba district, Himachal Pradesh
- Total Capacity: 240 MW (3 x 80 MW units)
- Current Status:
- First 80 MW unit commissioned and supplying power
- Second 80 MW unit synchronized with the grid, undergoing trial runs
- Third 80 MW unit commissioning in progress
Power Purchase Agreement
The Kutehr project is backed by a long-term Power Purchase Agreement (PPA) with Haryana Power Purchase Centre (HPPC), showcasing the following key features:
- Duration: 35 years (with provisions for extension)
- Capacity: Entire 240 MW
- Tariff: Levelized ceiling tariff of ₹4.50/kWh
Impact on JSW Energy's Portfolio
With the commissioning of this new unit, JSW Energy has significantly bolstered its renewable energy capacity:
Energy Source | Installed Capacity |
---|---|
Hydro | 1,471 MW |
Solar | 2,157 MW |
Wind | 3,562 MW |
This addition has increased the share of renewables in JSW Energy's portfolio to 56%, aligning with the company's focus on sustainable power generation.
Strategic Importance
Sharad Mahendra, Joint Managing Director and CEO of JSW Energy, emphasized the strategic importance of this project, stating, "This achievement underscores our strong project execution capabilities and our commitment to delivering clean, sustainable power to the nation. The timing is especially opportune, coinciding with the peak monsoon season, enabling us to capitalise on high waterflow and reap the generation benefit in current fiscal."
Future Outlook
JSW Energy's commissioning of the Kutehr Hydroelectric Power Plant is part of its broader strategy to expand its green energy footprint. The company has set ambitious targets for the future:
- Total Locked-in Generation Capacity: 30.3 GW
- 12.8 GW operational
- 12.9 GW under construction
- 4.6 GW in pipeline
- Energy Storage Capacity: 29.4 GWh
- 26.4 GWh through hydro pumped storage projects
- 3.0 GWh through battery energy storage systems
JSW Energy aims to reach a generation capacity of 30 GW and an energy storage capacity of 40 GWh by FY 2030, with the ultimate goal of achieving Carbon Neutrality by 2050.
The successful commissioning of the Kutehr Hydroelectric Power Plant not only strengthens JSW Energy's position in the renewable energy sector but also contributes to India's clean energy objectives. As the company continues to expand its green energy portfolio, it is poised to play a significant role in the country's transition towards a more sustainable power generation mix.