Rhetan TMT completes 1 MW solar project; generation by Aug 2026
Rhetan TMT Limited completed the installation of a 1 MW captive solar project in Kadi, Gujarat, securing GEDA and NHAI approvals. Power generation is slated for early August 2026, aiming to reduce energy costs and enhance sustainability credentials alongside recent BIS certifications.

*this image is generated using AI for illustrative purposes only.
Rhetan TMT has completed the installation of its 1 MW (AC) captive ground-mounted solar power project at its manufacturing facility in Kadi, Gujarat. The company announced on July 27, 2026, that it has cleared all regulatory milestones, including final registration from the Gujarat Energy Development Agency (GEDA) under the Gujarat Renewable Energy Policy, 2023, and permission from the National Highways Authority of India (NHAI) for laying underground electrical cables across a National Highway. Power generation is expected to commence by the end of the first week of August 2026. This initiative aims to convert volatile energy input costs into stable, self-owned assets, strengthening operational efficiency for the steel manufacturer.
The disclosure was made under Regulation 30 of the SEBI (Listing Obligations and Disclosure Requirements) Regulations, 2015. It serves as a continuation of an earlier communication dated February 15, 2025, when the project was initially announced. Shalin Shah, Managing Director of Rhetan TMT Limited, confirmed that testing and commissioning activities are currently underway and are expected to conclude within weeks. The company emphasized that this execution demonstrates management's ability to deliver strategic initiatives on schedule, moving from announcement to completed installation over seventeen months.
Regulatory and Execution Milestones
The project achieved three critical milestones leading to its current status:
| Milestone | Status | Details |
|---|---|---|
| GEDA Registration | Secured | Final registration received from Gujarat Energy Development Agency under Gujarat Renewable Energy Policy, 2023 |
| NHAI Permission | Secured | Permission obtained for laying underground electrical cable across National Highway |
| Installation | Completed | Physical installation finished; testing and commissioning underway |
Strategic Implications
Rhetan TMT stated that power is among the most significant input costs in steel manufacturing. By establishing captive solar generation, the company aims to optimize energy costs and strengthen operational efficiency, with benefits compounding over the life of the asset. The move aligns with India’s broader clean-energy transition targeting 500 GW of non-fossil fuel capacity by 2030, positioning Rhetan TMT as a steel manufacturer building its own green energy backbone.
The company highlighted that this project transitions it towards sustainable steel manufacturing, an attribute increasingly valued by institutional investors and large customers. This initiative unfolds alongside the company’s recent BIS certification for premium TMT grades, representing a simultaneous upgrade in product quality and production cost structure. Rhetan TMT Limited will inform the exchanges and shareholders of further material developments regarding the commissioning process.
Historical Stock Returns for Rhetan TMT
| 1 Day | 5 Days | 1 Month | 6 Months | 1 Year | 5 Years |
|---|---|---|---|---|---|
| +2.33% | +3.46% | +5.61% | +10.85% | +36.26% | +36.26% |
What is the projected annual cost savings for Rhetan TMT once the 1 MW solar plant reaches full operational capacity?
Will Rhetan TMT pursue additional renewable energy projects or expand this facility to meet a larger percentage of its total energy consumption?
How might the combination of captive solar power and recent BIS certification impact Rhetan TMT's competitiveness against larger steel manufacturers with established green credentials?