NHPC secures ₹392.31 crore arbitral award in BGS-SGS-SOMA dispute

scanx
Reviewed by
Anirudha BScanX News Team
Key Highlights
  • NHPC received an arbitral award of ₹392.31 crore and €15.36 lakh from BGS-SGS-SOMA
  • The award was pronounced by the Arbitral Tribunal on September 1, 2026
  • The dispute relates to construction work for the Subansiri Lower HE project
  • The awarded amount includes interest at 10% from September 2021 to August 2026
  • CERC regulations allow the recovery to be treated as project cost and recovered via tariff
powered bylight_fuzz_icon
49900258

*this image is generated using AI for illustrative purposes only.

NHPC Limited secured an arbitral award of ₹392.31 crore and €15.36 lakh from BGS-SGS-SOMA, the company disclosed. The Arbitral Tribunal pronounced the award on September 1, 2026, resolving a long-standing litigation matter related to the Subansiri Lower Hydroelectric Project.

Arbitration outcome details

The award pertains to the construction of diversion tunnels, coffer dams, concrete gravity dam, plunge pool, and cut-off wall (Lot SSL-1) of the Subansiri Lower HE project (2000 MW). BGS-SGS-SOMA had originally claimed ₹796.87 crore and €28.76 lakh for the work.

The following table summarises the claim versus the awarded amount:

Parameter Details
Counterparty BGS-SGS-SOMA
Original Claim (INR) ₹796.87 crore
Original Claim (EUR) €28.76 lakh
Awarded Amount (INR) ₹392.31 crore
Awarded Amount (EUR) €15.36 lakh
Award Date September 1, 2026

The awarded sum includes the principal amount plus interest at 10% per annum calculated from September 9, 2021, to August 31, 2026.

Regulatory and financial implications

In compliance with Regulation 30 of the SEBI (Listing Obligations and Disclosure Requirements) Regulations, 2015, NHPC informed the stock exchanges about the change in the status of this material litigation case. The disclosure was made in continuation of a previous letter dated August 14, 2023.

Crucially, NHPC stated that as per the Central Electricity Regulatory Commission (CERC) Tariff Regulations, 2024, the awarded amount is allowable as project cost. This means the recovery is recoverable through tariff, providing a clear path for monetisation without impacting the company’s immediate cash flow from operations negatively.

What the Numbers Show

The arbitral award represents approximately 49% of the original claimed amount of ₹796.87 crore. While the principal recovery is less than half of the initial claim, the inclusion of interest at 10% over nearly five years underscores the time value of money in prolonged arbitration proceedings. The ability to recover this amount through tariffs ensures that the financial impact is neutralised over the project's life cycle rather than bearing an immediate P&L hit.

Historical Stock Returns for NHPC

1 Day5 Days1 Month6 Months1 Year5 Years
-0.85%-1.27%-3.91%+0.42%-3.70%+178.12%

How will the inclusion of this ₹392.31 crore award in the project cost impact NHPC's future tariff revisions and revenue stability?

What is the expected timeline for the actual realization of cash flows from BGS-SGS-SOMA following the September 2026 arbitral award?

Does this resolution eliminate all remaining litigation risks associated with the Subansiri Lower Hydroelectric Project, or are other disputes still pending?

NHPC ESG score drops to 57 from 61 following Teesta VI incident

scanx
Reviewed by
Ashish TScanX News Team
Key Highlights
  • S&P Global revised NHPC’s ESG score down to 57 as on August 28, 2026
  • Previous score was 61, awarded in February 2026
  • Reduction driven by Teesta VI HEP incident on July 20, 2026
  • Social and Governance scores fell; Environment score unchanged
  • NHPC has sought justification from the rating agency
powered bylight_fuzz_icon
49568143

*this image is generated using AI for illustrative purposes only.

NHPC Limited disclosed a revision in its Environmental, Social and Governance (ESG) score by S&P Global. The rating agency updated the score to 57 as on August 28, 2026, down from the previous score of 61 awarded in February 2026.

The downgrade stems from the 'Media and Stakeholder Analysis' of the Teesta VI Hydroelectric Project (HEP) incident that occurred on July 20, 2026. NHPC informed stock exchanges about the change in compliance with Regulation 30 of the SEBI (Listing Obligations and Disclosure Requirements) Regulations, 2015.

Score Breakdown

The total ESG score reduction reflects specific declines in two of the three pillars:

Pillar Status
Social (S) Reduced
Governance (G) Reduced
Environment (E) No change

The Environmental pillar score remained unchanged despite the overall drop.

Company Response

NHPC has raised its concerns with S&P Global regarding the deduction. The company has requested appropriate justification for the reduction in its ESG score. This disclosure follows an earlier communication dated February 14, 2026.

Historical Stock Returns for NHPC

1 Day5 Days1 Month6 Months1 Year5 Years
-0.85%-1.27%-3.91%+0.42%-3.70%+178.12%

How might the revised ESG score impact NHPC's eligibility for green financing or sustainability-linked loans in the near term?

What specific remedial actions is NHPC implementing to address the Social and Governance deficiencies highlighted by the Teesta VI incident?

Will other major rating agencies like MSCI or Sustainalytics follow suit with similar downgrades, potentially affecting institutional investor sentiment?

More News on NHPC

1 Year Returns:-3.70%