NTBCL Issues Official Statement on DND Flyway Delay to February 2026 Due to GRAP-IV

2 min read     Updated on 02 Jan 2026, 12:50 PM
scanx
Reviewed by
Naman SScanX News Team
Overview

Noida Toll Bridge Company Limited has issued an official media release confirming the delay of DND Flyway upgradation work until February 2026, citing GRAP-IV restrictions that prohibit polluting construction activities and technical requirements for specific temperature conditions during certain phases of the work.

28884007

*this image is generated using AI for illustrative purposes only.

Noida Toll Bridge Company Limited (NTBCL) has officially announced through a media release that its DND Flyway upgradation project will be delayed until February 2026. The infrastructure company cited GRAP-IV restrictions and technical temperature requirements as primary factors affecting the construction timeline.

Official Project Timeline Update

NTBCL had initially planned to complete the DND Flyway upgradation work between December 2025 and January 2026. The company had commenced preliminary activities in the third week of October 2025 after completing all preparatory work, including material procurement, manpower allocation, and detailed execution plans for the entire stretch.

Parameter: Original Plan Revised Timeline
Project Start: October 2025 (3rd week) December 2025
Expected Completion: December 2025 - January 2026 February 2026
Delay Duration: - 5 weeks
Work Resumption: - Post GRAP-IV lifting

Impact of GRAP-IV Restrictions

The Graded Response Action Plan (GRAP-IV) measures, implemented due to hazardous air quality conditions across the National Capital Region, have significantly impacted the project timeline. Road improvement work is classified as polluting activity and cannot be undertaken while GRAP-IV restrictions are in force.

The statutory restrictions under GRAP-IV have prohibited upgradation activities and allied work, resulting in the work commencement timeline being pushed from October to December 2025, creating a delay of nearly five weeks.

Technical Temperature Requirements

Beyond regulatory restrictions, NTBCL revealed that certain upgradation work originally scheduled for November cannot be carried out in the cold December temperatures prevalent in the NCR region. These specific construction activities require particular temperature environments for proper completion.

Technical Factor: Details
Temperature Dependency: Specific work requires optimal temperature
Risk of Poor Conditions: Sub-par outcomes in cold weather
Rescheduled Timeline: January 2026 for temperature-sensitive work
Quality Assurance: Work postponed to maintain standards

The company emphasized that continuation of work in the absence of suitable environmental conditions may lead to sub-par outcomes, necessitating the postponement of this phase to January 2026.

Company's Commitment and Compliance

As a responsible infrastructure operator, NTBCL stated it remains fully compliant with all applicable directives issued by authorities. The company expressed its firm commitment to maintaining DND Flyway to world-class infrastructure standards, ensuring commuter safety and smooth traffic movement.

Once GRAP-IV measures are lifted and conditions become conducive for road upgradation activities, the work is expected to be completed within approximately five weeks, which may extend the completion timeline into February 2026. The company assured stakeholders that any adjustments to timelines arising from external factors are temporary in nature and committed to keeping stakeholders and commuters appropriately informed as the situation evolves.

Historical Stock Returns for Noida Toll Bridge

1 Day5 Days1 Month6 Months1 Year5 Years
+3.10%+2.84%0.0%+7.55%-11.14%-32.94%

Noida Toll Bridge Shareholders Approve CEO Remuneration with 87.61% Majority Vote

2 min read     Updated on 17 Dec 2025, 12:39 PM
scanx
Reviewed by
Riya DScanX News Team
Overview

Noida Toll Bridge Company Limited shareholders have overwhelmingly approved the ₹50.00 lakhs annual remuneration package for Executive Director & CEO Dheeraj Kumar through postal ballot, with 87.61% of votes cast in favor. The voting process concluded on January 17, 2026, with 56.55 million valid votes cast representing 30.37% of total shareholding, while the promoter group provided unanimous support with 100% approval rate.

27500953

*this image is generated using AI for illustrative purposes only.

Noida Toll Bridge Company Limited shareholders have approved the remuneration package for Executive Director and Chief Executive Officer Mr. Dheeraj Kumar through postal ballot, with the resolution receiving overwhelming support from the voting shareholders.

Postal Ballot Results

The postal ballot process concluded with strong shareholder support for the proposed remuneration structure. The scrutinizer's report, submitted by Mr. Sanjay Kumar of Kumar Wadhwa & Company, revealed decisive approval for the executive compensation package.

Voting Category Votes in Favor Votes Against Total Valid Votes Approval Rate
All Shareholders 49,542,895 7,003,814 56,546,709 87.61%
Promoter Group 49,095,007 0 49,095,007 100.00%
Public Non-Institutions 447,888 7,003,814 7,451,702 6.01%

Approved Remuneration Package

The shareholders endorsed the comprehensive compensation structure recommended by the Board of Directors and Nomination and Remuneration Committee for Mr. Dheeraj Kumar's executive role.

Component Details
Annual Remuneration ₹50.00 lakhs
Additional Benefits Applicable taxes and out-of-pocket expenses
Effective Date December 5, 2025
Director Identification Number 07046151
Resolution Type Ordinary Resolution

Voting Process and Timeline

The postal ballot process was conducted through National Securities Depository Limited (NSDL) e-voting platform, with Mr. Sanjay Kumar (FCS No. 9211, CP No. 7027) serving as the appointed scrutinizer.

Process Parameter Details
E-voting Period December 19, 2025 to January 17, 2026
Cut-off Date December 12, 2025
Total Shareholders on Record 59,343
Result Declaration January 19, 2026
Voting Participation 30.37% of total shareholding

Executive Profile and Responsibilities

Mr. Dheeraj Kumar brings over two decades of experience in project and corporate finance across infrastructure sectors. His expertise encompasses economics and finance with specialization in project development, infrastructure finance from conceptualization to closure stages, and business planning development.

The Executive Director & CEO oversees day-to-day business operations, revenue-related contracts, operational and maintenance activities, and ongoing litigation matters. Mr. Kumar also serves as a member of the company's Audit Committee, contributing to the organization's governance framework.

The resolution, having received the requisite majority approval, is deemed effective from January 17, 2026, the last date of remote e-voting. The company has communicated the results to BSE Limited and made them available on the company website and NSDL's e-voting portal in compliance with regulatory requirements.

Historical Stock Returns for Noida Toll Bridge

1 Day5 Days1 Month6 Months1 Year5 Years
+3.10%+2.84%0.0%+7.55%-11.14%-32.94%

More News on Noida Toll Bridge

1 Year Returns:-11.14%