NTBCL Issues Official Statement on DND Flyway Delay to February 2026 Due to GRAP-IV
Noida Toll Bridge Company Limited has issued an official media release confirming the delay of DND Flyway upgradation work until February 2026, citing GRAP-IV restrictions that prohibit polluting construction activities and technical requirements for specific temperature conditions during certain phases of the work.

*this image is generated using AI for illustrative purposes only.
Noida Toll Bridge Company Limited (NTBCL) has officially announced through a media release that its DND Flyway upgradation project will be delayed until February 2026. The infrastructure company cited GRAP-IV restrictions and technical temperature requirements as primary factors affecting the construction timeline.
Official Project Timeline Update
NTBCL had initially planned to complete the DND Flyway upgradation work between December 2025 and January 2026. The company had commenced preliminary activities in the third week of October 2025 after completing all preparatory work, including material procurement, manpower allocation, and detailed execution plans for the entire stretch.
| Parameter: | Original Plan | Revised Timeline |
|---|---|---|
| Project Start: | October 2025 (3rd week) | December 2025 |
| Expected Completion: | December 2025 - January 2026 | February 2026 |
| Delay Duration: | - | 5 weeks |
| Work Resumption: | - | Post GRAP-IV lifting |
Impact of GRAP-IV Restrictions
The Graded Response Action Plan (GRAP-IV) measures, implemented due to hazardous air quality conditions across the National Capital Region, have significantly impacted the project timeline. Road improvement work is classified as polluting activity and cannot be undertaken while GRAP-IV restrictions are in force.
The statutory restrictions under GRAP-IV have prohibited upgradation activities and allied work, resulting in the work commencement timeline being pushed from October to December 2025, creating a delay of nearly five weeks.
Technical Temperature Requirements
Beyond regulatory restrictions, NTBCL revealed that certain upgradation work originally scheduled for November cannot be carried out in the cold December temperatures prevalent in the NCR region. These specific construction activities require particular temperature environments for proper completion.
| Technical Factor: | Details |
|---|---|
| Temperature Dependency: | Specific work requires optimal temperature |
| Risk of Poor Conditions: | Sub-par outcomes in cold weather |
| Rescheduled Timeline: | January 2026 for temperature-sensitive work |
| Quality Assurance: | Work postponed to maintain standards |
The company emphasized that continuation of work in the absence of suitable environmental conditions may lead to sub-par outcomes, necessitating the postponement of this phase to January 2026.
Company's Commitment and Compliance
As a responsible infrastructure operator, NTBCL stated it remains fully compliant with all applicable directives issued by authorities. The company expressed its firm commitment to maintaining DND Flyway to world-class infrastructure standards, ensuring commuter safety and smooth traffic movement.
Once GRAP-IV measures are lifted and conditions become conducive for road upgradation activities, the work is expected to be completed within approximately five weeks, which may extend the completion timeline into February 2026. The company assured stakeholders that any adjustments to timelines arising from external factors are temporary in nature and committed to keeping stakeholders and commuters appropriately informed as the situation evolves.
Historical Stock Returns for Noida Toll Bridge
| 1 Day | 5 Days | 1 Month | 6 Months | 1 Year | 5 Years |
|---|---|---|---|---|---|
| -0.25% | -6.45% | -13.43% | -3.56% | -63.26% | -43.22% |
































