High Court Sets Aside Arbitral Award, Orders Customer To Refund ₹218.46 Crore To Thermax
Thermax secured a major legal victory as the Bombay High Court set aside an arbitral award from June 2023 that had imposed substantial financial liabilities on the company. The court ordered the customer to refund ₹218.46 crores with 6% interest, reversing the original award that required Thermax to pay ₹173.72 crores in compensation and repair costs.

*this image is generated using AI for illustrative purposes only.
Thermax has achieved a significant legal victory as the Bombay High Court set aside an arbitral award that was previously passed against the company. The court's decision reverses a substantial financial liability and instead orders the customer to refund the deposited amount along with interest.
Arbitral Award Background
The original arbitral award dated June 5, 2023, had directed Thermax to undertake costly remedial work and pay substantial compensation to a customer. The arbitral tribunal, consisting of a sole arbitrator, had ruled that the company must repair and reinstate two Gas Turbo Generators (GTGs) at the customer's plant at Thermax's own cost under the defect liability clause.
| Original Award Details: | Amount |
|---|---|
| Power Expenditure Compensation: | ₹173.72 crores |
| Arbitration Costs: | ₹0.95 crores |
| Estimated Total Impact: | ₹250 crores |
| Repair Obligation: | Two GTGs at company cost |
High Court Judgment
The Bombay High Court has completely overturned the arbitral award, delivering a favorable outcome for Thermax. The court's judgment not only sets aside the previous award but also mandates the customer to refund the entire deposit amount that Thermax had made during the arbitration proceedings.
| Court Order Details: | Specifications |
|---|---|
| Refund Amount: | ₹218.46 crores |
| Interest Rate: | 6% per annum |
| Stay Period: | Four weeks |
| Beneficiary: | Thermax Limited |
| Paying Entity: | Customer (Claimant) |
Legal Timeline and Next Steps
Following the High Court's ruling, the customer has sought a stay on the judgment's operation. The court has granted a four-week stay period to allow the customer to pursue their appellate remedy. This temporary stay provides the customer with time to file an appeal in a higher court if they choose to challenge the High Court's decision.
Financial Impact
The court's decision represents a substantial positive financial development for Thermax. The company will receive ₹218.46 crores along with 6% per annum interest, marking a significant cash inflow once the stay period concludes and payment is processed. This outcome eliminates the estimated ₹250 crore financial impact that the original arbitral award would have imposed on the company.
Historical Stock Returns for Thermax
| 1 Day | 5 Days | 1 Month | 6 Months | 1 Year | 5 Years |
|---|---|---|---|---|---|
| +0.44% | -2.89% | -12.05% | -21.53% | -41.37% | +205.49% |















































