GAIL Revises KKBMPL Pipeline Project Completion Schedule to March 2026

1 min read     Updated on 03 Jan 2026, 04:52 PM
scanx
Reviewed by
Riya DScanX News Team
Overview

GAIL (India) Limited has revised the completion schedule for its Kochi-Koottanad-Bengaluru-Mangaluru Pipeline (KKBMPL) project from December 2025 to March 2026. The 1,104 km pipeline project has 884 km laid and 628 km commissioned, with balance work under construction. The revision was approved by the Board on January 03, 2026, citing delays in availability of hindrance-free fronts as the primary reason.

28984944

*this image is generated using AI for illustrative purposes only.

GAIL (India) Limited has announced a revision in the completion schedule for its major pipeline infrastructure project, extending the timeline due to construction challenges. The Maharatna company disclosed this development under Regulation 30 of SEBI LODR Regulations, 2015, following Board approval on January 03, 2026.

Project Details and Current Status

The Kochi-Koottanad-Bengaluru-Mangaluru Pipeline (KKBMPL) project represents a significant infrastructure development in India's gas distribution network. The project details and current progress are outlined below:

Parameter: Details
Pipeline Name: Kochi-Koottanad-Bengaluru-Mangaluru Pipeline (KKBMPL)
Authorized Length: 1,104 km
Pipeline Laid: 884 km
Pipeline Commissioned: 628 km
Remaining Construction: Balance work under construction

Schedule Revision Details

The company has revised the completion timeline for the remaining construction work on the KKBMPL project. The schedule adjustment reflects operational challenges encountered during the construction phase.

Timeline Aspect: Details
Original Completion: December 2025
Revised Completion: March 2026
Scope: Balance under construction
Additional Investment: Not Applicable
Primary Reason: Delay in availability of hindrance free fronts

Board Approval and Regulatory Compliance

The revision in completion schedule received formal approval from GAIL's Board of Directors during their meeting on January 03, 2026. The board meeting commenced at 02:00 p.m. and concluded at 04:30 p.m., where directors reviewed and approved the timeline adjustment.

The disclosure was made in compliance with SEBI (Listing Obligations and Disclosure Requirements) Regulations, 2015, ensuring transparency with stakeholders and regulatory authorities. The company has communicated this development to both the National Stock Exchange of India Limited and BSE Limited, where GAIL shares are listed under scrip codes GAIL-EQ and 532155 respectively.

Construction Challenges

The primary factor contributing to the schedule revision is the delay in availability of hindrance-free fronts for construction activities. This challenge is common in large-scale pipeline projects that traverse diverse geographical terrains and require coordination with multiple stakeholders for land access and clearances.

With 884 km of the total 1,104 km pipeline already laid and 628 km commissioned, the project has achieved substantial progress. The remaining construction work is now scheduled for completion by March 2026, representing a three-month extension from the original December 2025 timeline.

Historical Stock Returns for GAIL

1 Day5 Days1 Month6 Months1 Year5 Years
-1.33%+1.19%-1.11%-9.28%-9.45%+102.80%

GAIL Revises Srikakulam Angul Pipeline Project Completion Schedule to June 2026

1 min read     Updated on 03 Jan 2026, 04:47 PM
scanx
Reviewed by
Jubin VScanX News Team
Overview

GAIL (India) Limited has revised the completion schedule for its 744 km Srikakulam Angul Pipeline Project from December 2025 to June 2026. While the 422 km main pipeline was successfully commissioned on September 26, 2025, delays in forest working permissions for 56 km of the 322 km spur line have necessitated the timeline extension. The company has completed 280 km of the spur pipeline, with tree cutting operations currently in progress following sequential approval of permissions through September 2025. The revision was approved by the Board of Directors on January 03, 2026, with no additional investment required.

28984637

*this image is generated using AI for illustrative purposes only.

GAIL (India) Limited has announced a revision in the completion schedule for its Srikakulam Angul Pipeline Project, extending the timeline from December 2025 to June 2026. The announcement was made through a regulatory disclosure under Regulation 30 of SEBI LODR Regulations, 2015, following approval by the company's Board of Directors on January 03, 2026.

Project Overview

The Srikakulam Angul Pipeline Project represents a significant infrastructure development comprising a total length of 744 km. The project is structured in two main components: a 422 km main pipeline and a 322 km spur pipeline, designed to enhance the natural gas distribution network in the region.

Component: Length Status
Main Pipeline: 422 km Commissioned on September 26, 2025
Spur Pipeline: 322 km 280 km completed, 42 km pending
Total Project: 744 km Revised completion: June 2026

Completion Status and Challenges

The main pipeline component has achieved full operational status, with the entire 422 km length commissioned on September 26, 2025. However, progress on the spur line has encountered regulatory delays that necessitated the schedule revision.

For the 322 km spur pipeline, GAIL has successfully completed 280 km of construction. The remaining work has been impacted by delays in obtaining forest working permissions for a 56 km stretch of the pipeline route.

Regulatory Approval Timeline

The company faced sequential approval challenges that affected project execution:

  • Forest working permissions were received progressively until June 23, 2025
  • Tree cutting permissions followed sequentially through September 2025
  • Tree cutting operations are currently in progress for the affected sections

These regulatory processes have directly contributed to the six-month extension in the project completion timeline.

Board Approval and Compliance

The schedule revision received formal approval from GAIL's Board of Directors during their meeting held on January 03, 2026. The meeting commenced at 2:00 PM and concluded at 4:30 PM, with the decision forming part of the company's compliance obligations under SEBI listing regulations.

The disclosure emphasizes that no additional investment is required for the revised completion schedule, indicating that the delay is primarily operational rather than financial in nature. This project revision reflects the complex regulatory environment surrounding infrastructure development in India, particularly for projects traversing forest areas that require multiple levels of environmental clearances.