GAIL Revises KKBMPL Pipeline Project Completion Schedule to March 2026
GAIL (India) Limited has revised the completion schedule for its Kochi-Koottanad-Bengaluru-Mangaluru Pipeline (KKBMPL) project from December 2025 to March 2026. The 1,104 km pipeline project has 884 km laid and 628 km commissioned, with balance work under construction. The revision was approved by the Board on January 03, 2026, citing delays in availability of hindrance-free fronts as the primary reason.

*this image is generated using AI for illustrative purposes only.
GAIL (India) Limited has announced a revision in the completion schedule for its major pipeline infrastructure project, extending the timeline due to construction challenges. The Maharatna company disclosed this development under Regulation 30 of SEBI LODR Regulations, 2015, following Board approval on January 03, 2026.
Project Details and Current Status
The Kochi-Koottanad-Bengaluru-Mangaluru Pipeline (KKBMPL) project represents a significant infrastructure development in India's gas distribution network. The project details and current progress are outlined below:
| Parameter: | Details |
|---|---|
| Pipeline Name: | Kochi-Koottanad-Bengaluru-Mangaluru Pipeline (KKBMPL) |
| Authorized Length: | 1,104 km |
| Pipeline Laid: | 884 km |
| Pipeline Commissioned: | 628 km |
| Remaining Construction: | Balance work under construction |
Schedule Revision Details
The company has revised the completion timeline for the remaining construction work on the KKBMPL project. The schedule adjustment reflects operational challenges encountered during the construction phase.
| Timeline Aspect: | Details |
|---|---|
| Original Completion: | December 2025 |
| Revised Completion: | March 2026 |
| Scope: | Balance under construction |
| Additional Investment: | Not Applicable |
| Primary Reason: | Delay in availability of hindrance free fronts |
Board Approval and Regulatory Compliance
The revision in completion schedule received formal approval from GAIL's Board of Directors during their meeting on January 03, 2026. The board meeting commenced at 02:00 p.m. and concluded at 04:30 p.m., where directors reviewed and approved the timeline adjustment.
The disclosure was made in compliance with SEBI (Listing Obligations and Disclosure Requirements) Regulations, 2015, ensuring transparency with stakeholders and regulatory authorities. The company has communicated this development to both the National Stock Exchange of India Limited and BSE Limited, where GAIL shares are listed under scrip codes GAIL-EQ and 532155 respectively.
Construction Challenges
The primary factor contributing to the schedule revision is the delay in availability of hindrance-free fronts for construction activities. This challenge is common in large-scale pipeline projects that traverse diverse geographical terrains and require coordination with multiple stakeholders for land access and clearances.
With 884 km of the total 1,104 km pipeline already laid and 628 km commissioned, the project has achieved substantial progress. The remaining construction work is now scheduled for completion by March 2026, representing a three-month extension from the original December 2025 timeline.