GAIL Delays MNJPL Project to December 2025, Approves ₹5,364 Crore Jamnagar LPG Pipeline Expansion
GAIL's Board of Directors has approved a ₹5,363.88 crore expansion project for the Jamnagar-Loni Petroleum Product Pipeline (JLPL). The project will increase the pipeline's capacity from 3.25 MMTPA to 6.5 MMTPA. The expansion is set to be completed within 36 months from July 23, 2025. GAIL has also extended the completion date for the Mumbai-Nagpur-Jharsuguda Pipeline (MNJPL) project to December 31, 2025. These infrastructure developments aim to meet India's growing energy demands and strengthen the country's gas pipeline network.

*this image is generated using AI for illustrative purposes only.
GAIL (India) Limited , the country's largest gas transmission and distribution company, has announced a significant expansion project for its Jamnagar-Loni Petroleum Product (LPG) Pipeline (JLPL). The company's Board of Directors has approved a capacity expansion plan that will double the pipeline's capacity from 3.25 MMTPA (Million Metric Tonnes Per Annum) to 6.5 MMTPA.
Project Details
The expansion project comes with a price tag of ₹5,363.88 crore and will be financed through a combination of debt and equity. This strategic move is aimed at supporting GAIL's business growth and meeting the increasing demand for LPG transportation.
Current Capacity and Utilization
According to the disclosure made by GAIL under Regulation 30 of SEBI (LODR) Regulations, 2015, the current capacity utilization of the Jamnagar-Loni LPG Pipeline stands at 3.22 MMTPA, nearly maxing out its existing capacity of 3.25 MMTPA. This high utilization rate underscores the need for expansion to accommodate future growth.
Project Timeline
The expansion project is set to be completed within 36 months from July 23, 2025, following the authorization from the Petroleum and Natural Gas Regulatory Board (PNGRB). This timeline suggests that the expanded pipeline capacity should be operational by mid-2028, barring any unforeseen delays.
Strategic Importance
The Jamnagar-Loni LPG Pipeline plays a crucial role in the transportation of liquefied petroleum gas across several states in India. The doubling of its capacity is expected to significantly enhance GAIL's ability to meet the growing energy demands of the country, particularly in the LPG sector.
Additional Infrastructure Updates
GAIL has also revised the completion schedule for another significant project - the Mumbai-Nagpur-Jharsuguda Pipeline (MNJPL). The 1,702 km MNJPL project, which includes three sections, has seen its completion date extended from September 30, 2025, to December 31, 2025.
The MNJPL project update reveals:
- Most of the construction is mechanically complete, awaiting regulatory approvals from PESO (Petroleum and Explosives Safety Organisation).
- The Mumbai–Nagpur section is finished and ready.
- Small portions totaling around 11 km remain incomplete across different stretches.
These infrastructure developments underscore GAIL's commitment to expanding and strengthening India's gas pipeline network, which is crucial for the country's energy security and economic growth.
As GAIL continues to invest in its pipeline infrastructure, these projects are expected to play a vital role in meeting India's growing energy needs and supporting the transition towards cleaner fuel options.
In the stock market, GAIL shares were trading 1.60% lower at ₹175.80 following these announcements.