NTPC Green Energy commissions 68.22 MW Dahod solar, 9.45 MW Vanki wind
- NTPC Green Energy commissioned 68.22 MW at Dahod Solar effective July 23, 2026
- A further 9.45 MW from Vanki Wind went on commercial operation on September 19, 2026
- Total installed capacity for NTPC Green Energy group rises to 10,920.53 MW
- The projects are executed by stepdown subsidiary NTPC Renewable Energy Limited

*this image is generated using AI for illustrative purposes only.
A subsidiary of NTPC Green Energy has commissioned two renewable energy projects, adding 77.67 MW of combined capacity and lifting the company's total installed capacity to 10,920.53 MW.
Project milestone details
The latest developments mark significant steps in the phased development of two key projects executed through NTPC Renewable Energy Limited, a stepdown subsidiary.
The third phase of the 200 MW Dahod Solar Project in Gujarat, with a capacity of 68.22 MW, was declared on commercial operation effective July 23, 2026. This follows the certificate issued by the Gujarat Energy Development Agency dated September 17, 2026.
Simultaneously, the third part capacity of 9.45 MW of the Vanki Wind Energy Project located in Nakhatrana, Kutch, Gujarat, was declared on commercial operation effective September 19, 2026.
The table below summarises the key parameters of these commissioning events:
| Parameter | Details |
|---|---|
| Project 1 | 200 MW Dahod Solar Project (Gujarat) |
| Capacity added (Dahod) | 68.22 MW |
| Commercial operation date (Dahod) | July 23, 2026 |
| Project 2 | Vanki Wind Energy Project (Kutch, Gujarat) |
| Capacity added (Vanki) | 9.45 MW |
| Commercial operation date (Vanki) | September 19, 2026 |
| Total installed capacity post-addition | 10,920.53 MW |
Capacity expansion in context
With the addition of 68.22 MW from the Dahod phase, NTPC Green Energy's total capacity initially stood at 10,911.08 MW. The subsequent addition of 9.45 MW from the Vanki wind project brings the final total installed capacity of the NTPC Green Energy Limited group to 10,920.53 MW.
At the parent level, NTPC Limited disclosed that the total installed capacity of the NTPC group stands at 91,164 MW, with commercial capacity at 90,084 MW following these declarations.
Historical Stock Returns for NTPC Green Energy
| 1 Day | 5 Days | 1 Month | 6 Months | 1 Year | 5 Years |
|---|---|---|---|---|---|
| +1.11% | +0.95% | -3.90% | -7.88% | -14.92% | -27.21% |
How will the completion of the Dahod Solar Project's third phase impact NTPC Green Energy's revenue projections for the upcoming fiscal year?
What is the timeline for the remaining phases of the Vanki Wind Energy Project, and how does this align with Gujarat's state-level renewable energy targets?
Given the increase in total installed capacity, what are NTPC Green Energy's plans for grid integration and potential curtailment risks in the Gujarat region?