Lcc Projects wins Rs 70.35 crore order from Reliance Industries for Kutch substation works
- Lcc Projects secured a Rs 70.35 crore order from Reliance Industries Limited for civil works at Kutch RE Project – Z2.
- The contract includes construction of 400kV Main Pooling GIS Substation (9 months) and 400kV Mobile GIS 1 Substation (4 months).
- This follows a Rs 653.34 crore order from the Chief Engineer Water Resources Zone, Kota, won on 24 Sep 2026.
- Total order inflow for Q2FY27 stands at Rs 723.69 crore across two distinct clients.
- Company FY26 revenue was Rs 3639.50 crore with an OPM of 13.38%.

*this image is generated using AI for illustrative purposes only.
Lcc Projects has received a Letter of Commitment for Civil Works valued at Rs 70.35 crore from Reliance Industries Limited. The project covers the construction of the 400kV Main Pooling GIS Substation and 400kV Mobile GIS 1 Substation at Kutch, Gujarat, under the Kutch RE Project – Z2.
Order Details and Timeline
The new contract is classified as significant and was disclosed to the exchange on 26.09.2026. The execution timeline for the Main Pooling GIS Substation is 9 months, while the Mobile GIS 1 Substation has a timeline of 4 months. This order marks a diversification of the company's client base, moving beyond government water resources departments to private sector energy majors.
Recent Order History
This new award follows closely on the heels of a major order won by the company earlier this month. On 24.09.2026, Lcc Projects emerged as the L-1 bidder for a work order valued at Rs 653.34 crore from the Chief Engineer Water Resources Zone, Kota (Rajasthan). That contract involves the construction of the Chhoti Kalisindh Medium Irrigation Project on a turnkey basis.
The company has now disclosed two orders totaling Rs 723.69 crore in the current quarter (Q2FY27). Previously, there were no disclosed orders in the preceding three fiscal quarters.
| Date | Value (Rs Cr) | Awarding Entity | Project Scope |
|---|---|---|---|
| 26 Sep 2026 | 70.35 | Reliance Industries Limited | Civil Works for 400kV Substations at Kutch |
| 24 Sep 2026 | 653.34 | Chief Engineer Water Resources Zone, Kota | Chhoti Kalisindh Medium Irrigation Project |
Company Order Track Record
The pre-computed summary for Q2FY27 (Jul-Sep 2026) reflects the total order inflow of Rs 653.34 crore initially reported. With the addition of the Reliance Industries order, the quarterly inflow increases significantly. The distinct key awarding entities for the quarter now include both the Chief Engineer Water Resources Zone, Kota (Raj.) and Reliance Industries Limited.
Financial Context and Execution Capacity
The company's consolidated revenue for FY26 stood at Rs 3639.50 crore, with a net profit of Rs 286.40 crore. Operating Profit Margin (OPM) improved to 13.38% in FY26 from 12.96% in FY25. The new orders contribute to future revenue recognition, with the Reliance project having a shorter execution cycle compared to the multi-year irrigation project.
| Quarter | Revenue (Rs Cr) | Net Profit (Rs Cr) | OPM (%) |
|---|---|---|---|
| FY26 | 3639.50 | 286.40 | 13.38% |
| FY25 | 2941.00 | 223.60 | 12.96% |
| FY24 | 2449.80 | 122.00 | 10.91% |
Working Capital and Valuation
The company maintains a Current Ratio of 1.46x, suggesting adequate liquidity for short-term obligations. Total Liabilities/Equity stands at 1.74x, indicating moderate leverage when considering trade payables and other non-debt liabilities. Operating Cashflow turned positive at Rs 158.40 crore in FY26, up from Rs 23.60 crore in FY25.
As of 26 Sep 2026, the stock trades at a P/E of 14.6x against an ROCE of 46.86%. The market capitalization is recorded at ₹4320.16 Cr. The addition of these orders provides visibility into near-term revenue streams, particularly from the shorter-duration Reliance contract.
Historical Stock Returns for LCC Projects
| 1 Day | 5 Days | 1 Month | 6 Months | 1 Year | 5 Years |
|---|---|---|---|---|---|
| -1.52% | +3.70% | +4.12% | +4.12% | +4.12% | +4.12% |