Borana Weaves 9.9 MW Hybrid Power Project delayed to Aug 2026
Borana Weaves Limited reported that the commissioning of its 9.9 MW Hybrid Power Project in Gujarat is delayed to August 2026 from May 31, 2026. The delay, attributed to high wind speeds, fuel shortages, and transmission line shutdown issues, was communicated by developer Clean Max Enviro Energy Solutions Limited.

*this image is generated using AI for illustrative purposes only.
Borana Weaves Limited has informed the exchanges that the commissioning of its 9.9 MW Hybrid Power Project at Kalikanagar, Gujarat, has been delayed to the end of August 2026. The project was previously scheduled for commissioning by May 31, 2026. This delay impacts the company's operational timeline for the renewable energy initiative. The disclosure was made pursuant to Regulation 30 of the SEBI (Listing Obligations and Disclosure Requirements) Regulations, 2015.
Project Details
The following table summarises the key details of the delayed hybrid power project:
| Project Detail: | Information |
|---|---|
| Project Name: | 9.9 MW Hybrid Power Project |
| Location: | Kalikanagar, Gujarat |
| Original Commissioning Date: | May 31, 2026 |
| Revised Commissioning Date: | End of August 2026 |
| Developer: | Clean Max Enviro Energy Solutions Limited |
Reasons for Delay
The company received a communication dated June 18, 2026, from Clean Max Enviro Energy Solutions Limited, the project developer, outlining the revised timeline. Clean Max Enviro Energy Solutions Limited cited several factors for the delay. High wind speeds halted the erection of Wind Turbine Generators (WTG). Additionally, a shortage of fuel at the site and the inability to secure timely shutdowns of existing 33 KV and 11 KV lines from a private developer and GETCO/PGVCL for 33 KV transmission line work contributed to the postponement.
The communication from the project manager at Clean Max Enviro Energy Solutions Limited confirmed that the revised timeline is tentative and subject to the completion of the pending transmission line work and resolution of the site constraints.
Historical Stock Returns for Borana Weaves
| 1 Day | 5 Days | 1 Month | 6 Months | 1 Year | 5 Years |
|---|---|---|---|---|---|
| -2.36% | -4.41% | -4.92% | +2.68% | +38.24% | +19.32% |
What financial penalties, if any, will Borana Weaves incur due to this three-month extension?
How will the delay in commissioning affect Borana Weaves' projected cost savings from renewable energy adoption?
Is there a risk of further delays beyond August 2026 given the tentative nature of the revised timeline?

































