ACME Solar Holdings Commissions Additional 33.333 MW/160.484 MWh BESS Capacity in Rajasthan
ACME Solar Holdings Limited, through its wholly owned subsidiary ACME Sun Power Private Limited, has commissioned an additional 33.333 MW/160.484 MWh Battery Energy Storage System (BESS) capacity at Village Badi Sid, Rajasthan, on May 11, 2026, with a Commercial Operation Date of May 13, 2026. This brings the subsidiary's total commissioned capacity to 233.336 MW/1123.424 MWh, as disclosed under Regulation 30 of SEBI's Listing Obligations and Disclosure Requirements Regulations.

*this image is generated using AI for illustrative purposes only.
ACME Solar Holdings Limited has announced the commissioning of an additional 33.333 MW/160.484 MWh capacity of its Battery Energy Storage System (BESS) project through its wholly owned subsidiary, ACME Sun Power Private Limited. The development was disclosed under Regulation 30 of the Securities and Exchange Board of India (Listing Obligations and Disclosure Requirements) Regulations, 2015, as amended, and follows the company's earlier intimation dated May 04, 2026.
Project Commissioning Details
The newly commissioned BESS capacity is located at Village Badi Sid, Tehsil-Bap, Dist: Phalodi and Jodhpur, Rajasthan. The commissioning was completed on May 11, 2026, with the Commercial Operation Date (COD) scheduled for May 13, 2026. The key details of this commissioning are summarised below:
| Parameter: | Details |
|---|---|
| Commissioned Capacity: | 33.333 MW / 160.484 MWh |
| Project Type: | Battery Energy Storage System (BESS) |
| Location: | Village Badi Sid, Tehsil-Bap, Dist: Phalodi and Jodhpur, Rajasthan |
| Commissioning Date: | May 11, 2026 |
| Commercial Operation Date (COD): | May 13, 2026 |
| Subsidiary: | ACME Sun Power Private Limited |
Cumulative Commissioned Capacity
With the addition of this latest capacity, ACME Sun Power Private Limited has reached a total commissioned capacity of 233.336 MW/1123.424 MWh. The table below highlights the capacity position following this commissioning:
| Metric: | Capacity |
|---|---|
| Additional Capacity Commissioned: | 33.333 MW / 160.484 MWh |
| Total Commissioned Capacity: | 233.336 MW / 1123.424 MWh |
The disclosure was signed by Rajesh Sodhi, Company Secretary and Compliance Officer of ACME Solar Holdings Limited, on May 11, 2026.
Historical Stock Returns for ACME Solar Holdings
| 1 Day | 5 Days | 1 Month | 6 Months | 1 Year | 5 Years |
|---|---|---|---|---|---|
| -0.44% | -4.38% | +5.17% | +10.72% | +27.71% | +11.61% |
What is ACME Solar Holdings' remaining pipeline of BESS capacity yet to be commissioned, and what is the expected timeline for full project completion?
How will the 233.336 MW/1123.424 MWh cumulative BESS capacity impact ACME Solar's revenue visibility and long-term power purchase agreements with grid operators?
Could ACME Solar's expanding BESS footprint in Rajasthan position it to bid for upcoming government renewable energy storage tenders in the region?