GAIL (India): Company Plans 178.2 MW Wind Project in Maharashtra with ₹1,736 Crore Investment Over Two Years
GAIL (India) Limited received board approval for establishing a 178.2 MW wind energy project in Maharashtra with an investment of ₹1,736.25 crores. The project will be financed through debt and equity, scheduled for completion within 24 months from LSTK contract award, and will more than double the company's existing wind capacity of 117.95 MW.

*this image is generated using AI for illustrative purposes only.
GAIL (India) Limited has received board approval for a major renewable energy expansion with the establishment of a greenfield 178.2 MW wind project in Maharashtra. The board of directors approved this significant investment during their meeting, which commenced at 4:00 p.m. and concluded at 5:30 p.m.
Project Investment and Financing
The wind energy project requires a substantial investment of ₹1,736.25 crores and will be financed through a combination of debt and equity. This investment underscores the company's commitment to expanding its renewable energy footprint as part of its broader business growth strategy.
Capacity Expansion Details
The project details reveal a significant expansion of GAIL's wind energy capabilities:
| Parameter: | Details |
|---|---|
| Existing Capacity: | 117.95 MW |
| Current Utilization: | Full Capacity |
| Proposed Addition: | 178.2 MW |
| Total Investment: | ₹1,736.25 Crores |
| Financing Mode: | Debt and Equity |
| Timeline: | 24 months from LSTK contract award |
Implementation Timeline
The proposed capacity addition of 178.2 MW is scheduled to be completed within 24 months from the award of the Lump Sum Turnkey (LSTK) contract. This timeline reflects the company's commitment to efficient project execution and rapid deployment of renewable energy infrastructure.
Strategic Rationale
The wind project aligns with GAIL's business growth objectives and represents a strategic move to enhance the company's renewable energy portfolio. With existing wind capacity of 117.95 MW operating at full utilization, the new project will more than double the company's wind energy generation capability.
Regulatory Compliance
This disclosure has been made in compliance with Regulation 30 of SEBI (Listing Obligations and Disclosure Requirements) Regulations, 2015. The announcement was signed by Company Secretary Mahesh Kumar Agarwal and communicated to both the National Stock Exchange of India Limited and BSE Limited.
Historical Stock Returns for GAIL
| 1 Day | 5 Days | 1 Month | 6 Months | 1 Year | 5 Years |
|---|---|---|---|---|---|
| -0.25% | +1.59% | +5.42% | -1.23% | +6.38% | +79.34% |