Ashoka Buildcon Reports Mixed Q2 Results Amid Project Cancellation
Ashoka Buildcon Limited experienced a significant financial downturn in Q2 FY2025-26, with net profit falling 82.91% to ₹781.00 million and revenue decreasing 25.70% to ₹18.50 billion year-over-year. EBITDA declined 35.91% to ₹5.80 billion. Additionally, the company faced the cancellation of a ₹288.18 crore MMRDA infrastructure project due to administrative reasons, including revised alignment and cost escalation. Ashoka Buildcon stressed that the cancellation was unrelated to their performance or capabilities.

*this image is generated using AI for illustrative purposes only.
Ashoka Buildcon Limited , a prominent infrastructure development company, has reported mixed financial results for the second quarter of the fiscal year 2025-26, while also facing a significant project cancellation.
Financial Performance
The company's Q2 results showed a notable decline in key financial metrics:
| Metric | Q2 FY2025-26 | Q2 FY2024-25 | YoY Change |
|---|---|---|---|
| EBITDA | ₹5.80 billion | ₹9.05 billion | -35.91% |
| EBITDA Margin | 31.60% | 36.37% | -4.77% |
| Net Profit | ₹781.00 million | ₹4.57 billion | -82.91% |
| Revenue | ₹18.50 billion | ₹24.90 billion | -25.70% |
The substantial decrease in net profit and revenue indicates challenging market conditions for the company during this quarter.
Project Cancellation
In a separate development, Ashoka Buildcon announced the cancellation of a significant infrastructure project. The project, awarded by the Mumbai Metropolitan Region Development Authority (MMRDA) in October 2024, involved the design and construction of a creek bridge from Kolshet to Kalher, with a contract value of ₹288.18 crore plus GST.
The cancellation was attributed to administrative reasons by MMRDA, specifically:
- Revised alignment deviating from the original bid document
- Alterations to the originally sanctioned scope of work
- A 39% increase in deck area
- Overall cost escalation of 33.5%
MMRDA stated that these changes constituted a significant deviation from the approved contractual scope, necessitating the cancellation and re-invitation of bids for the project.
Company Statement
Ashoka Buildcon emphasized that the project cancellation was solely due to MMRDA's administrative reasons and not related to the company's performance, capability, or contractual compliance. The financial impact of this cancellation is yet to be fully evaluated by the company.
Looking Ahead
Despite the setback with the MMRDA project, Ashoka Buildcon continues to maintain a presence in the infrastructure sector. The company's ability to navigate these challenges and secure new projects may be crucial for its performance in the coming quarters.
Investors and stakeholders will likely monitor how Ashoka Buildcon addresses the revenue decline and adapts its strategy in light of the recent project cancellation.