Chandni Machines starts aluminium ingot project in Rajkot with ₹150 lakh capex
- Chandni Machines commences aluminium ingot manufacturing project at Kuvada GIDC, Rajkot
- Capital expenditure for machinery stands at ₹150 lakh with trial production set for September 2026
- Facility targets monthly capacity of 300 tonnes, generating estimated revenue of ₹9.45 crore
- Commercial production scheduled to begin from October 1, 2026 subject to regulatory approvals
- Company evaluates two-fold capacity expansion by March 2027 based on initial performance

*this image is generated using AI for illustrative purposes only.
Chandni Machines has commenced implementation of its aluminium ingot manufacturing project at Kuvada GIDC, Rajkot. The company targets commercial production from October 1, 2026.
The initiative marks a strategic diversification into the non-ferrous metals value chain. Management has leased a 22,000 sq. ft. industrial facility and placed orders for machinery aggregating ₹150 lakh. Trial production is scheduled for September 2026, subject to regulatory approvals.
Project Execution Timeline
The company outlined specific milestones for the facility setup:
- Infrastructure: Leased factory building with existing electricity connection of approximately 37 KW.
- Machinery: Installation targeted for completion by September 20, 2026.
- Manpower: Engaged approximately 30 contractual workers; construction of quarters for 50 workers underway.
- Regulatory: Consent to Operate applied for; expected by September 10, 2026.
Revenue and Capacity Estimates
Upon stabilization, the facility aims to produce approximately 300 tonnes of aluminium ingots per month. Based on an indicative average realisation of ₹315 per kg, the project is expected to generate approximately ₹9.45 crore in monthly revenue.
| Metric | Estimate |
|---|---|
| Monthly Capacity | 300 tonnes |
| Monthly Revenue | ₹9.45 crore |
| Indicative Price | ₹315 per kg |
| Estimated Net Profit | ₹50 lakh per month |
These figures rely on current management assumptions regarding raw material costs and market conditions. Actual results may vary based on aluminium prices and operational efficiency.
Future Expansion Plans
Chandni Machines is evaluating a two-fold expansion of the proposed capacity by March 2027. This scaling depends on business performance, market demand, and resource availability. The expansion aims to strengthen manufacturing capabilities within the aluminium sector.
What the Numbers Show
The projected net profit of approximately ₹50 lakh per month represents roughly 5.3% of the estimated monthly revenue of ₹9.45 crore. This margin assumption is critical to the project's viability, as it relies heavily on the indicative realisation price of ₹315 per kg remaining stable against volatile aluminium market rates.
Historical Stock Returns for Chandni Machines
| 1 Day | 5 Days | 1 Month | 6 Months | 1 Year | 5 Years |
|---|---|---|---|---|---|
| -0.05% | -2.82% | -5.36% | +53.31% | +177.36% | 0.0% |
How will fluctuations in global aluminium prices impact the projected 5.3% net profit margin if the indicative realisation price of ₹315 per kg deviates?
What specific hedging strategies or raw material sourcing agreements has Chandni Machines established to mitigate volatility in input costs for the ingot manufacturing project?
How does the proposed capacity expansion to 600 tonnes by March 2027 align with current downstream demand trends in the non-ferrous metals sector?