Deccan Gold Advances Altyn Tor Gold Project, Targets October 2025 for Commercial Production
Deccan Gold Mines Limited has provided an update on its Altyn Tor Gold Project in Kyrgyzstan. The company aims to begin commercial operations from the gravity circuit by mid to late October 2025. Key progress includes commissioning of conveyor systems, successful trial runs of crushing equipment, ongoing ball mill installation, and advancement in power infrastructure. The project faces potential risks from early winter conditions, but contingency measures are in place. The Altyn Tor deposit has estimated mineral resources of 4.65 Mt at 1.21 g/t Au, containing 180 koz of gold.

*this image is generated using AI for illustrative purposes only.
Deccan Gold Mines Limited has provided a comprehensive update on the progress of its Altyn Tor Gold Project in Kyrgyzstan, signaling significant advancements towards commercial production. The company aims to begin commercial operations from the gravity circuit by mid to late October 2025, marking a crucial milestone in the project's development.
Project Milestones and Progress
Processing Plant Upgrades
- Conveyor System: 11 conveyor units have been successfully commissioned, with additional units for ball mill feed and tailing feed in transit.
- Crushing Equipment: Jaw and cone crushers have completed successful trial runs.
- Ball Mill Installation: Ongoing, with completion targeted for late August to early September 2025.
- Gravity Concentrator: Equipment is on-site, with commercial production from the gravity circuit aimed for mid to late October 2025.
- Leaching System: Tanks fabricated and painted, with full erection expected by mid to late October.
Power Infrastructure
- A 2500 kVA diesel generator set has been ordered for October delivery to power the ball mill during commissioning.
- High-tension powerline installation contract awarded, targeting completion by late November to early December.
Tailings Storage Facility (TSF)
- Excavation of the new tailings dam has commenced, scheduled for completion in October 2025.
- Geomembrane lining planned for November and December, weather permitting.
Mining Operations
- Approximately 30,000 m³ of waste removed to date.
- Target of 100,000 m³ waste removal set for the next 2-3 months.
Resource Development
- Drilling programme has completed about 2,000m of the planned 2,500m.
- Multiple zones of mineralisation identified, including visible gold.
Project Outlook and Challenges
Dr. Hanuma Prasad Modali, Managing Director of Deccan Gold, expressed cautious optimism about meeting target timelines while acknowledging potential risks:
"We are pleased with progress and are cautiously optimistic of achieving our target timelines for completing the process plant, power lines, and tailings dam as per our schedule. As usual in these latitudes, early onset of winter poses the greatest risk for construction projects."
The company is implementing contingency measures to mitigate the impact of potential early winter conditions, including:
- Erecting sheds to protect critical equipment
- Monitoring shipments and aligning civil works with equipment deliveries
- Focusing on commencing Dore bar production from the gravity circuit in October
- Prioritizing the completion of high-tension power line and substation works in November
About Altyn Tor Gold Project
The Altyn Tor deposit is located in the highly mineralized Soltan Sary gold mineralization zone, part of the major Tien Shen Shear Zone. Current mineral resources are estimated at:
Resource Category | Tonnage (Mt) | Grade (g/t Au) | Contained Gold (koz) |
---|---|---|---|
Total Resources | 4.65 | 1.21 | 180 |
This estimate includes 1.4 Mt (51 koz) of tailings and low-grade stockpile material, using a 0.5 g/t Au cut-off grade.
Deccan Gold's investment in the Altyn Tor Gold Project through Avelum Partners marks the first investment by an Indian mining and exploration company in Kyrgyzstan, potentially enhancing economic ties between the two countries.
As Deccan Gold progresses towards its production goals, the company remains committed to ethical and responsible mining practices, aiming to set new standards in the industry while contributing to sustainable development in the region.
Historical Stock Returns for Deccan Gold Mines
1 Day | 5 Days | 1 Month | 6 Months | 1 Year | 5 Years |
---|---|---|---|---|---|
-0.28% | -3.62% | -9.06% | +15.79% | -16.83% | +767.45% |