Palisades restart project completes major phase
Holtec International announced the Palisades restart project transitioned from large-scale activities to routine maintenance and testing on July 02, 2026. Key milestones include placing the turbine-generator on turning gear and completing fuel handling system upgrades. The site is preparing for startup with over 5,000 work activities remaining.

*this image is generated using AI for illustrative purposes only.
Holtec International announced on July 02, 2026, that the Palisades restart project has successfully transitioned from large-scale construction activities to the final phase of routine maintenance, testing, and operational readiness. This shift marks a watershed moment in the historic effort to reopen the nuclear facility, with over 5,000 individual work activities still pending before startup. The completion of major projects underscores significant progress toward restoring the plant to safe and reliable operation.
Among the final accomplishments in this project phase was the placement of the plant's turbine-generator on turning gear. This step followed extensive inspections, maintenance, testing, and refurbishment activities. Additionally, the installation and testing of a new state-of-the-art fuel handling machine were completed, finalizing the upgraded fuel handling system.
These projects represent the culmination of major efforts across the station. The restart initiative included reactor vessel inspections, replacement of reactor head penetrations, primary system chemical decontamination and passivation, steam generator tube refurbishment, and secondary-side cleaning. Other critical tasks involved fuel receipt and inspection, operator training and requalification, and numerous equipment upgrades and modernization projects.
Operational Readiness and Oversight
With the projects phase concluded, plant management has shifted focus to the Operations Command Center (OCC) and dedicated coordination teams. These teams are managing work around the clock to prepare the station for fuel load and startup. The OCC is overseeing the safe execution of remaining testing and verification activities.
The site has also engaged with senior leadership from the U.S. Nuclear Regulatory Commission (NRC). Commissioners Douglas Weaver and Bradley Crowell, along with senior staff from the Office of the Executive Director for Operations and the Office of the Chief Nuclear Reactor Inspector, toured the facility and received updates on restart activities.
Political Support and Strategic Impact
A bipartisan congressional delegation, including U.S. Representative Bill Huizenga and U.S. Representative Scott Peters, visited the site to review progress. Their visit highlights broad support from local, state, and federal leaders for the restart program. The return of the facility is expected to strengthen energy reliability and support jobs in Southwest Michigan.
Holtec Chairman and Chief Executive Officer Dr. Kris Singh emphasized the collaboration between government and private industry. The Palisades restart is the first-ever reopening of a U.S. nuclear facility. Holtec continues to focus on meeting all federal requirements and industry standards before the plant resumes operations.
What is the projected timeline for completing the remaining 5,000 work activities and achieving full commercial operation?
How will the NRC's recent site visit influence the final approval process for the plant's operational license?
What are the potential economic impacts on Southwest Michigan once the plant resumes full power generation?