Pace Digitek Wins ₹7,099.19 Million BESS EPC Contract
Pace Digitek Limited received a contract worth Rs. 7,099.19 Million from NLC India Renewables Limited for a 250 MW / 500 MWh BESS project. The scope includes turnkey EPC services and 12 years of O&M, with execution scheduled over 12 months from the Letter of Award date.

*this image is generated using AI for illustrative purposes only.
Pace Digitek Limited has secured a significant contract from NLC India Renewables Limited (NIRL) for the implementation of a Battery Energy Storage System (BESS) project. The contract, valued at Rs. 7,099.19 Million (including GST), was disclosed pursuant to Regulation 30 of the SEBI (Listing Obligations and Disclosure Requirements) Regulations, 2015. The intimation regarding this development was submitted to the stock exchanges on May 16, 2026.
Contract Overview
The awarded contract encompasses the Design, Engineering, Supply (excluding supply of Power Transformers), Manufacturing, Forwarding, Unloading, Storage at site, Erection, Testing & Commissioning on a turnkey basis. The project involves a cumulative capacity of 250 MW / 500 MWh Battery Energy Storage System (BESS). Additionally, the scope includes comprehensive Operation & Maintenance services for a period of 12 years from the Commercial Operation Declaration (COD). The project sites are located at Ottapidaram SS, Annupankulam SS, and Kayathar SS in Tamil Nadu.
The following table summarises the key details of the awarded contract:
| Parameter: | Details |
|---|---|
| Awarding Entity: | NLC India Renewables Limited (NIRL) |
| Contract Value: | Rs. 7,099.19 Million (including GST) |
| Project Capacity: | 250 MW / 500 MWh Battery Energy Storage System (BESS) |
| Project Locations: | Ottapidaram SS, Annupankulam SS and Kayathar SS, Tamil Nadu |
| Nature of Contract: | Turnkey EPC — Design, Engineering, Supply, Manufacturing, Erection, Testing & Commissioning |
| O&M Period: | 12 years from COD (Commercial Operation Declaration) |
| Execution Timeline: | 12 months from the date of Letter of Award |
| Domestic/International: | Domestic Entity |
| Related Party Transaction: | No |
| Promoter/Group Interest in Awarding Entity: | No |
Execution Timeline and Scope
The time schedule for the completion of the Commercial Operation Declaration (COD) for the entire capacity is set at 12 months from the date of the Letter of Award. Following the commissioning, the company will provide comprehensive Operation & Maintenance of the BESS System for a period of 12 years, effectively covering the BESS Service Life. The project is classified as a domestic order, and the company confirmed that neither the promoter, promoter group, nor group companies hold any interest in the awarding entity, NIRL.
Regulatory Disclosure
The intimation was submitted by Meghana M P, Company Secretary and Compliance Officer of Pace Digitek Limited. The disclosure was made in accordance with SEBI Circular No. SEBI/HO/CFD/CFD-PoD-1/P/CIR/2023/123 dated July 13, 2023. The company confirmed that the contract does not fall within the purview of related party transactions.
Historical Stock Returns for Pace Digitek
| 1 Day | 5 Days | 1 Month | 6 Months | 1 Year | 5 Years |
|---|---|---|---|---|---|
| +1.70% | -0.03% | -3.79% | -9.43% | -16.52% | -16.52% |
With cumulative Energy segment order wins approaching ₹1,00,000 million, what is Pace Digitek's target order book size for FY2027 and which sectors are expected to drive the next wave of wins?
How will the 12-year O&M contract structure impact Pace Digitek's recurring revenue profile and margin trajectory compared to its traditional EPC-only business model?
As India's BESS market scales rapidly, what supply chain or raw material risks could affect Pace Digitek's ability to execute the 12-month EPC timeline for the Tamil Nadu project?