Kernex Microsystems to complete CLW-II order by November 2026
Kernex Microsystems confirms 1,360 units delivered under CLW-II order, with remaining 1,664 units targeted for dispatch by November 2026. Installation and commissioning are scheduled for completion by February 2027. The update also outlines a four-year warranty provision and potential long-term AMC revenue streams.

*this image is generated using AI for illustrative purposes only.
Kernex Microsystems has provided a detailed progress update on its Chittaranjan Locomotive Works (CLW-II) order, confirming that execution is on track with a significant portion of units already delivered or in advanced stages of completion. The company anticipates fulfilling the entire order by November 2026.
CLW-II order execution status
The following table summarises the current status of units under the CLW-II order:
| Parameter: | Details |
|---|---|
| Total order quantity: | 3,024 |
| Units delivered: | 1,360 |
| Units remaining: | 1,664 |
| Units ready for dispatch: | 175 |
| Units almost finished: | 1,025 |
| Expected completion: | November 2026 |
Of the 1,664 units yet to be delivered, 175 units are ready for dispatch during the current month, while 1,025 units are described as almost finished (approximately 95% complete). Together, these two categories account for 1,200 units that are at or near completion, reflecting advanced progress on the outstanding portion of the order. The company has planned for a minimum of 500 units to be dispatched in each of September and October 2026.
Installation and warranty obligations
Upon completion of dispatches, Kernex Microsystems will have approximately two months, up to February 5, 2027, to complete balance installation and commissioning formalities. The contract includes a warranty period of four years from the date of issue of the completion certificate. The contract price is inclusive of this warranty obligation, with no separate consideration payable. In accordance with Ind AS 37, the company recognises a provision for expected warranty costs rather than recognising costs only when claims arise.
Following the warranty period, the company expects to earn Annual Maintenance Contract (AMC) revenue at approximately 3% of the capital cost per annum for 11 years, subject to contractual terms.
Diversification into other verticals
Beyond the CLW-II order, Kernex Microsystems is diversifying its business into other verticals. As part of this initiative, the company has secured an order amounting to approximately ₹15.90 crore, as previously intimated in May 2026.
Historical Stock Returns for Kernex Microsystems
| 1 Day | 5 Days | 1 Month | 6 Months | 1 Year | 5 Years |
|---|---|---|---|---|---|
| -13.46% | -28.55% | -20.12% | +50.81% | +58.24% | +2,182.35% |
How will the transition from manufacturing to the 11-year AMC phase impact Kernex Microsystems' revenue stability and margin profile post-2027?
What specific risks could delay the planned dispatch of 500 units per month in September and October 2026, and how might supply chain bottlenecks affect the November 2026 completion target?
Given the ₹15.90 crore order in a new vertical, what is the strategic roadmap for diversifying revenue streams to reduce dependency on the CLW-II contract?