Enviro Infra Engineers secures ₹256.92 crore orders for Varanasi STPs
Enviro Infra Engineers secured ₹256.92 crore EPC orders from Uttar Pradesh Jal Nigam (Rural) for 45 MLD and 60 MLD STPs in Varanasi under the Namami Gange Programme. The projects, valued at ₹126.78 crore and ₹130.14 crore respectively, will be developed under the Hybrid Annuity Model (HAM) with a 15-year O&M period. In-principle approvals for term loans have been secured for both projects.

*this image is generated using AI for illustrative purposes only.
Enviro Infra Engineers has secured EPC contracts worth ₹256.92 crore for energy-efficient sewage treatment infrastructure in Varanasi, Uttar Pradesh. The company received two orders from Uttar Pradesh Jal Nigam (Rural) under the Namami Gange Programme to develop 45 MLD and 60 MLD sewage treatment plants (STPs), expanding its Hybrid Annuity Model (HAM) portfolio to five projects. These wins strengthen the company's position in the water and wastewater treatment sector by integrating renewable energy solutions for operational sustainability.
Project Details
The contracts encompass the construction and operation of STPs at Pt. Deen Dayal Upadhyay Nagar (DDU Nagar) and Lohta. The projects will be executed as energy-efficient, self-sustaining facilities incorporating biogas-based and solar power generation systems to lower operating costs and reduce carbon emissions. The biogas power plant will convert sludge into biogas to generate electricity, while solar panels will produce clean daytime power.
| Particulars | Details |
|---|---|
| Awarding Entity: | Uttar Pradesh Jal Nigam (Rural) |
| Nature of Order: | Hybrid Annuity Model (HAM) with O&M |
| Project Locations: | Pt. Deen Dayal Upadhyay Nagar (DDU Nagar) and Lohta, Varanasi |
| Project Scope: | Development of 45 MLD and 60 MLD STPs and Associated Infrastructure |
| Order Value (DDU Nagar): | ₹126.78 crore (excluding GST) |
| Order Value (Lohta): | ₹130.14 crore (excluding GST) |
| Total Contract Value: | ₹256.92 crore |
Execution Timeline
The projects include an Operation and Maintenance (O&M) period of 15 years. The company confirmed that in-principle approvals for term loans have been secured for both projects to enable timely financial closure. The Lohta project will be executed through a special purpose vehicle (SPV), Varanasi Lohta STP Private Limited, incorporated by the company on June 17, 2026.
Management Commentary
Mr. Sanjay Jain, Chairman of Enviro Infra Engineers Limited, stated that the company is proud to be entrusted with these significant projects under the Namami Gange Programme. He emphasized the commitment to delivering high-quality, sustainable, and timely solutions that contribute to the nation’s water management and sanitation goals while maintaining the highest standards of engineering and execution.
Historical Stock Returns for Enviro Infra Engineers
| 1 Day | 5 Days | 1 Month | 6 Months | 1 Year | 5 Years |
|---|---|---|---|---|---|
| -3.74% | +5.48% | +28.26% | +15.25% | -0.48% | +11.79% |
How will the integration of biogas and solar power impact the long-term operational profitability of these projects?
Does this win signal a strategic shift for Enviro Infra towards prioritizing renewable energy integration in future EPC bids?