Ansal Properties Shares 49th Committee of Creditors Meeting Minutes for Fernhill Project
Ansal Properties and Infrastructure Limited filed minutes of its 49th Committee of Creditors meeting for the Fernhill Project held February 25, 2026, under CIRP proceedings. The meeting ratified previous appointments and expenses totaling ₹99,572, while addressing 16 ongoing litigation matters scheduled for March 2, 2026 hearing. The Hon'ble NCLT has directed no further adjournments will be entertained, and questioned the practice of inviting homebuyers as observers to CoC meetings.

*this image is generated using AI for illustrative purposes only.
Ansal Properties and Infrastructure Limited has filed the minutes of its 49th Committee of Creditors (CoC) meeting for the Fernhill Project, conducted on February 25, 2026, under the Corporate Insolvency Resolution Process (CIRP). The meeting was chaired by Resolution Professional Jalesh Kumar Grover and attended by the Authorized Representative of Home Buyers.
Meeting Composition and Attendance
The meeting was conducted through virtual mode at 12:30 PM with the following key participants:
| Participant Category | Name/Representative | Voting Share | Attendance |
|---|---|---|---|
| Resolution Professional | Jalesh Kumar Grover | Chairman | Physical |
| Home Buyers Representative | Ms. Aakriti Sood | 99.96% | Audio Visual |
| Unsecured Financial Creditor | Vinod Kumar and Babita Saini | 0.04% | Absent |
| Suspended Directors | Multiple Directors | - | Absent |
The meeting achieved the required quorum with Ms. Aakriti Sood representing 99.96% voting rights attending the proceedings. All suspended board directors remained absent from the meeting despite due service of notices.
Previous Meeting Ratifications
The committee approved the minutes of the 48th CoC meeting held on January 27, 2026, and took note of e-voting results on key agenda items. Two significant resolutions from the previous meeting received unanimous approval:
Site Manager Appointment: The committee ratified the appointment of Mr. Chimman Singh as Site Manager at ₹60,000 per month, along with additional expenses of ₹21,000 for accommodation charges.
CIRP Expenses: The committee approved expenses totaling ₹99,572 incurred during the CIRP period from December 1, 2025, to January 15, 2026, covering e-voting, security, and miscellaneous operational costs.
Litigation Status Update
The Resolution Professional provided comprehensive updates on 16 ongoing litigation matters, all scheduled for hearing on March 2, 2026. The Hon'ble NCLT has made it clear that no further adjournments will be entertained on the next hearing date.
| Case Type | Description | Current Status |
|---|---|---|
| Section 66 Applications | Against Piyare Lal Hari Singh Builders & Samyak Projects | Hearing on March 2, 2026 |
| Section 43 Application | Against Samyak Projects | Hearing on March 2, 2026 |
| Resolution Plan Approval | Under Section 30(6) | First hearing on March 2, 2026 |
| Criminal Revision | District Court Gurugram | Listed for April 15, 2026 |
The Resolution Professional noted that during the March 2 hearing, counsel will request the bench to hear the Resolution Plan to initiate working processes.
Corporate Governance Updates
The meeting addressed several governance matters including a resignation notification from Mr. Binay Kumar Singh, who served as Independent Non-Executive Director. The director had submitted Form DIR-11 in March 2025, though the corresponding statutory form remains unfiled by the company.
An email dated February 25, 2026, was received from company officials requesting attendance at the CoC meeting, but the Resolution Professional clarified that only directors are permitted to attend such meetings, not company officials.
NCLT Observations
During a recent hearing on February 25, 2026, the Hon'ble NCLT questioned the practice of inviting homebuyers as observers to CoC meetings when an Authorized Representative is already present. The bench directed the Resolution Professional to file an affidavit explaining the grounds for such invitations.
The Resolution Professional indicated that homebuyers attend only as observers since the matter primarily concerns them, and separate meetings for homebuyers are conducted by the Authorized Representative.
Project Background
The Fernhill Project, situated in District Gurgaon, Haryana, entered CIRP following the Hon'ble NCLAT order dated January 13, 2023, which confined the Section 7 application specifically to this project. The current Resolution Professional, Jalesh Kumar Grover, was appointed on January 10, 2024, and manages the project under CIRP proceedings.
The meeting concluded at 1:30 PM with a vote of thanks from the Chairman to all participants for their effective participation in the proceedings.