Orient Green Power Completes Erection of 6.6 MW Wind Turbines in Tamil Nadu
Orient Green Power Company Limited has achieved a significant milestone with its subsidiary Gamma Green Power completing the erection of 6.6 MW wind turbines in Tiruchirappalli District, Tamil Nadu. The company has received service connection and expects commissioning to be completed shortly, marking its entry into higher-capacity wind power generation with the remaining 3.3 MW capacity implementation in progress.

*this image is generated using AI for illustrative purposes only.
Orient Green Power Company Limited has achieved a significant milestone in its renewable energy expansion with the completion of erection of 6.6 MW wind turbines in Tamil Nadu. The company's subsidiary has successfully completed the installation and received service connection, marking substantial progress in its clean energy portfolio.
Project Completion Update
Gamma Green Power Private Limited, a subsidiary of Orient Green Power Company Limited, has completed the erection of 2 wind turbine generators of 3.3 MW each, aggregating to 6.6 MW capacity. The project has been developed through an Engineering, Procurement and Construction contract with Renfra Energy India Limited in Tiruchirappalli District, Tamil Nadu.
| Project Parameter: | Details |
|---|---|
| Completed Capacity: | 6.6 MW |
| Turbine Specifications: | 2 Nos. of 3.3 MW Envision make WTGs |
| Location: | Tiruchirappalli District, Tamil Nadu |
| Developer: | Gamma Green Power Private Limited |
| EPC Partner: | Renfra Energy India Limited |
| Service Connection: | Received March 20, 2026 |
Project Status and Timeline
The company has successfully received the service connection for the completed turbines. The remaining procedural formalities are currently being completed, with commissioning of the wind turbine generators expected to be completed shortly. This development represents the company's entry into power generation through higher-capacity wind turbine generators.
Overall Project Progress
The completion of the 6.6 MW installation brings significant progress toward the total project capacity of 9.9 MW. Implementation of the balance capacity of 3.3 MW is currently in progress, with the company committed to providing status updates in due course.
| Project Overview: | Details |
|---|---|
| Total Project Capacity: | 9.9 MW |
| Completed Capacity: | 6.6 MW |
| Remaining Capacity: | 3.3 MW |
| Project Status: | Implementation in Progress |
Strategic Significance
This milestone marks a key achievement for Orient Green Power Company Limited's renewable energy portfolio and represents the company's strategic entry into higher-capacity wind power generation. The successful completion of erection and receipt of service connection demonstrates the effectiveness of the partnership with Renfra Energy India Limited and positions the company to contribute meaningfully to Tamil Nadu's growing renewable energy capacity.