Atlanta Electricals Limited Receives Two-Year Debarment Order from South Bihar Power Distribution Company Limited
Atlanta Electricals Limited received a two-year debarment order from South Bihar Power Distribution Company Limited (SBPDCL) on 13th May 2026, related to the supply of 4 Nos. 10 MVA, 33/11 kV ONAN Power Transformers under a purchase order executed in FY2023-24, valued at less than ₹3 Crores. The order followed post-delivery short-circuit testing observations at CPRI, Bhopal, in May 2024, despite the transformer meeting all critical electrical, dielectric, thermal, and post-test performance parameters. The company has contested the order, submitted multiple technical representations, and requested independent re-testing, while clarifying that the debarment is limited to Bihar State Power Holding Company Limited tenders and is not a material event.

*this image is generated using AI for illustrative purposes only.
Atlanta Electricals Limited disclosed on 14th May 2026 that it has received a debarment order from South Bihar Power Distribution Company Limited (SBPDCL), barring the company from participating in SBPDCL-related tenders for a period of two years. The communication was received by the company on 13th May 2026 and pertains to a purchase order executed during FY2023-24. The company has stated that it respectfully disagrees with the characterisation of the matter and has already submitted detailed representations before the concerned authorities requesting reconsideration.
Key Details of the Debarment Order
The debarment order relates to the supply of power transformers under a purchase order whose value was less than ₹3 Crores. The following table summarises the key parameters of the matter:
| Parameter: | Details |
|---|---|
| Order Disclosure Date: | 14th May 2026 |
| Communication Received On: | 13th May 2026 |
| Debarment Order Date: | 24th April 2026 |
| Issuing Authority: | South Bihar Power Distribution Company Limited (SBPDCL) |
| Debarment Period: | Two years |
| Purchase Order Executed: | FY2023-24 |
| Order Value: | Less than ₹3 Crores |
| Equipment Supplied: | 4 Nos. 10 MVA, 33/11 kV ONAN Power Transformers |
| Testing Agency: | CPRI, Bhopal |
| Short-Circuit Testing Date: | May 2024 |
Background and Technical Context
The matter originated from post-delivery short-circuit testing conducted at CPRI, Bhopal, on one randomly selected transformer from the supplied lot in May 2024. According to the company, the transformer successfully withstood all short-circuit shots and met all major electrical, dielectric, thermal, and post-test performance parameters. However, during internal inspection after the completion of testing, the testing agency recorded certain observations relating to the displacement of insulating components.
Based on these observations, SBPDCL issued a Show Cause Notice dated 22nd August 2024. The company submitted detailed technical replies and representations on multiple occasions, as outlined below:
- 27th August 2024: Initial detailed technical reply submitted
- 30th October 2024: Further representation submitted
- 8th January 2025: Additional technical submission made
Following the submission on 8th January 2025, the company had not received any further communication for a considerable period and was engaged in discussions with the customer for technical resolution and reconsideration, before receiving the debarment order dated 24th April 2026.
Company's Position and Clarifications
Atlanta Electricals Limited has provided the following clarifications regarding the matter:
- The transformer had successfully cleared all critical test parameters during short-circuit testing.
- No operational abnormality or unsafe condition had been observed.
- The matter did not involve any established design failure or systemic quality issue.
- Transformers of the same design supplied earlier are operating satisfactorily in the field.
- The company has historically supplied 218 transformers of the same rating to Bihar utilities, all of which are working satisfactorily.
- The company has successfully short-circuit tested transformers of the same rating 13 times at CPRI in the past ten years for Bihar State Utilities.
- The order under reference was fully executed in FY2023-24 and its value was not material in relation to the scale of operations of the company.
- The matter pertains to a single isolated technical observation during post-test inspection.
The company also noted that industry practice in similar situations generally provides an opportunity for re-testing and/or independent technical evaluation before resorting to debarment. Accordingly, the company has requested the concerned authorities to permit re-testing and independent technical review of the transformer in question.
Scope and Next Steps
The company has clarified that the debarment order is limited to the tenders of Bihar State Power Holding Company Limited and does not constitute a material event. Atlanta Electricals Limited has stated that it does not affect its present or future business. The company has indicated that it will exercise legal options if necessary and will continue to update the stock exchanges regarding any material developments in the matter. The disclosure was made in the interest of transparency, good corporate governance, and adherence to compliance requirements under Regulation 30 of the SEBI (Listing Obligations and Disclosure Requirements) Regulations, 2015.

































